Deutsche Bahn has closed the Nuremberg–Ingolstadt high-speed line until Dec. 12, adding about 45 minutes to Munich–Berlin ICE trips, which now take roughly 4 hours 50 minutes.

White DB ICE train with a red stripe passing under a blue arch bridge on a four-track line near ForchheimAn ICE train on the four-track Nuremberg–Bamberg line near Forchheim. Photo: Deutsche Bahn AG

The full closure began at 10 p.m. on Oct. 30 and runs through Dec. 12, DB InfraGO said when it announced the rail renewal. Crews from the group’s infrastructure company are laying more than 160 kilometers (about 100 miles) of new rail between Allersberg, Kinding and Ingolstadt Nord and moving around 10,000 metric tons of material. High speeds on the line make rail replacement necessary after roughly 20 years, the company says.

The work also includes several new switches, new cabling, tunnel inspections and cleaning of drainage systems. A DB spokeswoman told German news agency dpa that the project costs around €70 million and that about 170 trains a day use the line, some at speeds of 300 km/h (186 mph).

ICE changes on Munich routes to Berlin, Hamburg and Frankfurt

DB’s long-distance timetable for the works applies from 7 a.m. on Oct. 30 to 11:59 p.m. on Dec. 12. Munich keeps at least one direct train an hour to Berlin, while services between Nuremberg and Berlin are unaffected. ICE line 18 via Augsburg runs as normal. Line 28 operates only between Nuremberg and Hamburg and no longer calls at Munich Hbf, and line 29 is diverted between Ingolstadt and Nuremberg, adding about 30 minutes and shifting its Munich–Nuremberg times.

Trains between Munich and Hamburg via Kassel run every two hours instead of hourly, and in the other hour they start or end in Nuremberg. On line 25, trains via Augsburg are unchanged, but those via Nuremberg skip both Munich Hbf and Ingolstadt Hbf. Ingolstadt still has an hourly ICE, though only to and from Berlin.

There are no direct Munich–Frankfurt trains via Nuremberg during the closure, and DB points travelers to direct services via Stuttgart. Line 41 runs only between Nuremberg and Essen or Dortmund, without its Munich stop.

ICE lines from Munich under DB’s long-distance timetable for the works, 7 a.m. Oct. 30 to 11:59 p.m. Dec. 12, 2026 (the line itself closed at 10 p.m. on Oct. 30): three lines lose their Munich Hbf stop on some or all trains, one is diverted and one runs as normal. Source: DB long-distance timetable notice

Line
Regular route
During the closure

ICE 18
Munich – Augsburg – Nuremberg – Erfurt – Berlin – Hamburg
Runs as normal

ICE 25
Munich – Augsburg or Nuremberg – Kassel – Hanover – Hamburg
Trains via Augsburg run as normal. Trains via Nuremberg run only between Nuremberg and Hamburg and skip Munich Hbf and Ingolstadt Hbf

ICE 28
Munich – Nuremberg – Erfurt – Leipzig – Berlin – Hamburg
Runs only between Nuremberg and Hamburg, no Munich Hbf stop

ICE 29
Munich – Ingolstadt – Nuremberg – Erfurt – Halle – Berlin
Diverted between Ingolstadt and Nuremberg, about 30 minutes longer, with changed Munich–Nuremberg times

ICE 41
Munich – Nuremberg – Frankfurt – Cologne – Essen – (Dortmund)
Runs only between Nuremberg and Essen or Dortmund, no Munich Hbf stop

RE1 trains rerouted and buses for Allersberg and Kinding

Regional RE1 trains between Munich, Ingolstadt and Nuremberg are diverted via Treuchtlingen (by way of Ingolstadt) or via Augsburg. Replacement buses run between Nuremberg and Ingolstadt, stopping at Allersberg and Allersberg (Rothsee) Johannisbrücke for RE1 and S5 passengers, and at Kinding, Kinding Marktplatz and Ingolstadt Nord for RE1 passengers.

Closure ends a day before DB’s 2027 timetable

The closure is scheduled to end on Dec. 12, one day before DB’s 2027 timetable takes effect on Dec. 13. The new timetable adds an ICE Sprinter line between Hamburg and Munich, running three times a day in each direction with stops only in Hanover and Nuremberg and cutting the journey by 20 minutes to 5 hours 20 minutes.