Region Stockholm has put a roughly 3 km section of the Tvärbanan light rail extension back out to tender as a build-only contract based on its own detailed designs.
Rendering of the planned Tvärbanan stop at Solvalla. Image: Region Stockholm
The procurement covers the stretch between Bromma Airport and Ursvik, where three new stops are planned at Solvalla, Rissne and Ursviks torg. Region Stockholm expects construction to begin in spring 2027 if everything goes to plan, after the work sites along the route have stood idle for just over two years.
Build-only contract for the Bromma Airport–Ursvik stretch
The contract combines civil works with track, power, signaling and telecommunications, grouped in Swedish practice as BEST works. In a build-only arrangement, the contractor works from detailed designs supplied by the client. Region Stockholm chose this model to gain control over the project. The region took charge of preparing the designs and hired new design consultants in spring 2025, whose work is now complete.
When the restart was approved in February 2026, the region said it had judged detailed design in its own hands to be the most cost-effective approach. The setup lets it procure several separate contracts and reduces the risk of further rework and changes during construction. Region Stockholm currently puts construction on the Bromma Airport–Ursvik stretch at about one and a half years.
Why the Gülermak contract was terminated in 2024
The earlier design-build contract with Gülermak, signed by SL in September 2020, covered the extension from Bromma Airport to Helenelund and was worth SEK 1.3 billion at signing. SL later canceled the Ursviks torg–Helenelund portion at the end of 2023, which reduced the contract value to about SEK 700 million.
Map of the existing Tvärbanan line and its planned extension to Helenelund. Graphic: Region Stockholm
SL terminated the contract with immediate effect in July 2024. Its main reason was that Gülermak had not provided the financial guarantees the contract required. SL also said the contractor had not paid subcontractors under the contract terms and that its deliveries had departed from budget on both cost and time.
Filippa Jansson, project manager for the Bromma–Ursvik section, said the termination raised many large questions, including what documentation the project could build on and what it was allowed to do in the unusual situation of a terminated contract. She added that the team felt pressure to be ready as quickly as possible but also had to weigh risks and make cost-effective choices.
Budget and opening dates for the Kista branch
The renewed implementation decision approved by the Regional Council on Feb. 17, 2026, sets a total budget of SEK 9.3 billion, of which SEK 9.2 billion is investment. Co-financing from the national government and municipalities is estimated at SEK 2.4 billion. Under that decision, service to Ursviks torg is expected to start in the fourth quarter of 2028 and service to Helenelund at the end of 2029, barring unforeseen events.
When the extension was first approved in 2016, its investment budget stood at SEK 4,937 million. From Bromma Airport, the extension runs about 7 km to Helenelund with eight new stops, passing through Rissne, Ursvik and Kista.
Kista branch of Tvärbanan: investment budget and planned opening by decision
Decision
Investment budget, SEK million
Planned opening to Helenelund
Implementation decision, 2016
4,937
2023
Renewed decision, 2022
6,522
2025
Renewed decision, Regional Council, June 2024
8,073
2026
Renewed decision, Regional Council, Feb. 17, 2026
9,179
End of 2029
Sources and notes
Investment amounts: traffic committee annual report 2025, auditors’ statement of March 2026, citing decisions RS 2021-0842 (2022) and RS 2025-1015 (2026). Planned openings to Helenelund for 2016–2024: KPMG review for Region Stockholm, May 2025. Planned opening for 2026: Region Stockholm, Feb. 2026. Intermediate openings to Norra Ursvik or Ursviks torg are not shown. Nominal amounts, not adjusted for inflation.
On the next segment, from Ursviks torg to Helenelund, preparatory work is underway in Kista. Construction there is also expected to start in 2027, and Region Stockholm estimates that this stretch will take about three years to build.