When Orsted announced plans to take full ownership of its Gunfleet Sands 1&2 UK offshore wind farm, Hamish Yates had more than one reason to take special note.

The deal to buy out minority investors in the 172MW of North Sea assets concerned a project for which Yates at one stage held P&L responsibility during his four years working at Orsted UK.

These days Yates is CEO at Neptune Infrastructure Associates, the asset management specialist he founded in 2023, and sees Gunfleet Sands as a marker of how Europe’s earliest large-scale wind farms – on and offshore – are spinning inexorably towards the end of their expected operational lives and out of fixed subsidy periods.

The benevolent conditions of the last decade gave developers and investors handsome rewards from backing new and early-stage projects.

Post-2022 and a far more challenging landscape – supply chain inflation, increased cost of capital, regulatory challenges – all raised the barriers and drove down margins.

In offshore wind in particular, the result, according to Yates, is an early-stage market increasingly reserved for the biggest financial players, noting the role of the likes of KKR and Apollo in recent offshore deals.

Yates claimed the older end of the wind spectrum presents opportunities for investors ready to take a less passive role in the secondary market for assets.

“If you can acquire a project for a significant discount because it’s nearing the end of its operational life and actually eke out returns over a much longer period than was expected before, then there’s an opportunity there.”

Hamish YatesHamish YatesPhoto: Neptune Infrastructure

That “takes a lot of technical expertise, a lot of data, relationships in [the] supply chain to Recharge News spare parts that maybe the OEM has stopped producing, so you need to go for aftermarket components. You need to be a bit more creative, so it’s not so much of a cookie-cutter approach, it has to be very specific to that project and the risks it faces and the revenue opportunities”.

Another untapped potential for UK offshore wind in particular lies in the lease, says Yates. “A lot of the older projects have significantly longer leases than the design life of the project. If you can, for example, do development for a repowering on the existing lease area there’s potential resale further down the line.

“Some projects have a 50-year lease but the project is only expected to last 20 to 25 years. So, there’s significant tail opportunity there.”

Yates added: “Compare the cost of these older leases with the brand-new ones and they’re night and day. The newer leases are going for an absolute fortune.”

If Yates was still at Orsted, for example, what would he be looking to do at Gunfleet Sands?

He believes Orsted’s move “makes a lot of sense”. With older assets there are big decisions to be made… and it’s much more straightforward to make [them] in a timeframe that works for you if you’re the sole shareholder”.

“[Gunfleet Sands’] 3.6MW Siemens turbines are really well understood, it’s in an interesting location. I think it’s a good test project for Orsted to really refine what it does with these late-life assets. More and more of [its] larger assets are going to get to this [point].”

He would be looking for “more creative ways to generate more revenues than were originally anticipated. Power prices have actually stayed pretty buoyant. So, how can you maximise that through an ancillary market, through creative PPAs?”

Looking at late-life options

Orsted paid about £15m to buy back from two Japanese partners the 49.9% of Gunfleet Sands 1&2 it did not own.

The Danish group said that will give it “greater flexibility in managing [the project] and assessing future late-life options, including a potential lifetime extension”.

Brought into service in 2010 and facing the expiry of its term under the UK’s Renewables Obligation scheme in 2029, Gunfleet Sands is among a clutch of ever-larger European offshore wind farms whose operators face big decisions – extend life, repower or decommission.

Matthew Simms, a director at Wood Thilsted, told Recharge that the options available will be highly case-specific for each project.

“Every wind farm has had a journey and some are obviously more ripe for lifetime extension than others,” said Simms, while stressing that a 25-year design life for a project is “not an expiry date” but an opportunity to build a case for continuing operation based on the data available now.

Simms pointed out that projects now are more aware of the future implications at end of expected life and are demanding, for example, more detailed data on foundations that can help owners make decisions later.

Marina Carrion, a specialist in life extension at DNV, agreed that structural integrity of projects will be one of the key factors determining the future of an ageing offshore wind asset, with filling in any gaps in data one of the priorities before a decision on options such as repowering can be made.

Carrion confirmed that the issue is increasingly front and centre for offshore wind. “This is going to be… a common discussion. And we’re seeing even for newer projects that are now being developed, or early stage projects, people are already starting thinking ‘are there any opportunities for life extension?’”