Revolution Wind, a 65-turbine wind farm south of Block Island, came fully online on Nov. 5 after nearly three years of construction. The project, owned by Orsted Rhode Island began supplying power to the grid in March while some turbines were still under construction and is now fully operational.

Despite intense opposition from the federal government and local groups in Rhode Island and Massachusetts, Revolution Wind began construction in 2023, and finished building its turbines last September. The undersea power cable transmits the energy produced by the turbines from their location 15 miles offshore at North Kingstown’s Port of Davisville. Orsted has invested about $35 million in a regional offshore wind logistics and operations hub at Quonset Point.

Citing the creation of good-paying jobs for union workers and a commitment to an “all-of-theabove energy strategy,” Gov. Dan McKee called it a “major win for Rhode Island’s workforce and our state’s energy future.”

The Revolution Wind array is capable of delivering up to 704 megawatts of power to the Rhode Island and Connecticut energy grids, which according to the company’s website is enough to power 350,000 homes.

However, the true measure of how many homes a specific energy project can power is difficult to determine, given how closely power companies guard some of their proprietary numbers. Different methodologies and assumptions about the multiple factors that go into the formula for determining power output can result in varying estimates.

For example, a 2025 analysis of one year of sales and production data from South Fork Wind, a 12-turbine array directly adjacent to the Revolution Wind lease, found that Orsted’s methodology for calculating the number of homes its project was powering on Long Island resulted in an over-estimate of 70,000. Long Island Power Authority’s estimate is about 53,000 homes.

Environmental advocates are celebrating the completion of the Revolution Wind project as a victory. Climate Action Rhode Island, an advocacy group that organized the statewide “Yes to Wind” campaign, is hosting a party at a local brewery on Nov. 20. A statement on the CARI website called the Revolution Wind and the Vineyard Wind project in Massachusetts a “major milestone for offshore wind in Rhode Island and across New England” and a “huge moment for our ‘Yes to Wind’ team and everyone who has worked to build public support for offshore wind.”

“This project is a huge milestone for our state and region, meeting 20 percent of R.I’.s electricity demand with the clean energy it generates,” said Avery Robertson, who works as the interim executive director of Climate Action Rhode Island and volunteers as the vice chair of Newport’s Energy & Environment Commission. Her 20 percent number is sourced from an Orsted fact sheet. “This project’s success means people will save money on their electricity bills, benefit from a more resilient grid with a more diverse energy mix, and lessen our dependence on fossil fuels which are driving climate change,” she said.

The National Wildlife Federation also issued a press release celebrating Revolution Wind’s fully operational status. “Revolution Wind is a win for wildlife and people in Rhode Island and Connecticut,” said Amber Hewett, the organization’s senior director of offshore wind energy. “National Wildlife Federation engaged throughout the permitting process for Revolution Wind and can attest to the strong protections for coastal and marine wildlife at every step of the process, from siting to construction to operations.”

The most prominent challenges to the project came from the federal government’s repeated efforts to shut it down. The Bureau of Ocean and Energy Management (BOEM) issued a stop-work order on Aug. 22, 2025. That order was lifted one month later after Orsted and the states of Rhode Island and Connecticut sued the Trump administration. A federal judge granted a preliminary injunction to temporarily halt the order and allow construction to continue.

The Department of the Interior suspended the project on Dec. 22, 2025, citing national security concerns. The project sued the federal government over that suspension and was granted a preliminary injunction on Jan. 12, allowing construction to resume immediately.

Most recently, the federal government joined a lawsuit that was initiated in 2024 by a Rhode Island the anti-wind group, Green Oceans. On Oct. 9, the government sought permission to rescind Revolution Wind’s construction and operations permit, which it had received in 2023. All turbine construction was already completed when the government made this filing.

Revolution Wind responded in an Oct. 26 filing: “Federal Defendants’ reversal unquestionably prejudices Revolution Wind’s interest in the project because it comes more than three years after BOEM approved the COP, after the project is fully constructed, providing power to New England and nearing full commercial operation, and after Revolution Wind has invested approximately $6 billion in reliance on the COP approval.”

The judge presiding over the case has repeatedly ruled in favor of Revolution Wind, ordering injunctions that have allowed the company to complete construction and bring its turbines fully online, despite the fact that litigation is ongoing. In its Oct. 26 filing, Revolution Wind requested the court issue summary judgment on the federal government’s attempt to remand its construction and operations permit no later than Dec. 1, 2026.