The array cables are the subsea power lines that will link the project’s 197 offshore wind turbines to Hornsea 3’s two offshore converter stations so that they can transport power back to shore.
These are an essential piece of the complex £8.5 billion infrastructure project that will generate 2.9 GW of renewable energy – enough to power more than 3.3 million UK homes.
Hornsea 3’s offshore wind turbines will generate electricity in the form of alternating current (AC). However, when AC is transmitted over long distances, particularly underwater, it loses power.
To increase efficiency, the AC electricity transmitted via the array cables will be converted at the offshore converter stations into direct current (DC) and then sent to shore via underwater export cables.
Cecilie Bak, project manager for Hornsea 3’s array cables, explained the lengthy engineering process it’s taken to get this far.
“First there was the tender process to find the right suppliers who could meet the complex manufacturing requirements for the array cables. It then took two years for two different suppliers to manufacture the enormous length of cables,” she said.
Cecilie Bak, project manager for Hornsea 3’s array cables (Image: Ørsted)
In the meantime, specialist teams had to prepare the seabed for the cable’s installation which required, among other things, the investigation of up to 4,000 targets and the removal of 2,300 boulders – all at a depth of approximately 25-70 metres below sea level in the North Sea.
The teams are now starting to lay the array cables on the seabed. They will then dig an installation trench for the cables to be placed in; and rocks will later be added in some spots to protect the cables further.
Once installed, the cables are connected to each end, tested to confirm they are working safely and correctly, and prepared for energisation. The whole process will take a little over a year.
“This is the crunch time and actual start of a new phase,” Cecilie said. “Seeing everything come together is what I’ve been looking forward to for the past four and a half years.”
She praised her team for remaining calm and focused while navigating the intense and complicated process. “It’s the people I’m proud of. The perseverance is crazy.”
The record-breaking Hornsea 3 will be the world’s single largest offshore wind farm upon completion.
Laying the array cables is another step toward delivering the UK more homegrown renewable energy at gigawatt scale.
For more information, visit hornseaproject3.co.uk
This story is also published in Insight Energy magazine, covering the latest news from the UK’s energy sector. Read the latest edition here.