The decision of the Court has immediate practical implications for any infrastructure business undertaking capital projects, particularly in sectors where extensive pre-development work is necessary or unavoidable.
Some points to consider include:
Assess what may still qualify
Despite confirming the narrowness of the test, the judgment does not preclude all pre-production expenditure from qualifying for capital allowances.
The ruling emphasises the importance of showing a sufficient proximity between the costs in question and the actual provision of the plant; of ensuring the costs incurred sit inside Lord Wilberforce’s “limiting curve”, rather than outside it. Whether or not that is the case will always be a question of fact and circumstance.
To illustrate, in this case, HMRC both:
(a) reserved its position on whether the cost of producing the final technical drawings and specifications which are then “made real” by the manufacturer could be recoverable, and
(b) accepted that if further surveys and studies were conducted during the final stages of fabrication or installation of the turbines, the costs incurred on those surveys and studies may qualify as being “on the provision of plant” either because, (i) they would then be part of the production process, or (ii) they would be part of the installation.
Review existing claims
Businesses with open capital allowance claims that include predevelopment costs should review those claims considering the narrowness of the test outlined in the ruling. Where such costs have been included as qualifying expenditure for capital allowance claims, there is now an elevated risk of challenge from HMRC.
Plan for future projects
For future projects, it is worth considering how contracts, procurement, and the phasing of work can be structured to (a) maximise the proportion of expenditure that falls within the narrower boundary established by the Court ruling, and (b) enhance protection for tax risk exposures.
The availability (or otherwise) of allowances will also affect project economics, pricing, and calculations of rates of return for investment projects.
Engage with policy development
There are two areas where UK tax policy is currently evolving in this area.
First, beginning in July 2026, HMRC will launch a new Advance Tax Certainty Service (ATCS). The ATCS is intended to provide major investment projects (with a lifetime qualifying project expenditure of at least £1bn) with legally binding certainty on tax treatment in advance. The service aims to support the government’s efforts to increase long-term economic growth in the UK, encouraging large-scale investment projects by providing up-front clarity on tax issues and reducing uncertainty for businesses. The ATCS will be available for capital allowance issues.
Second, at its first Budget (in autumn 2024), following a commitment in the Corporate Tax Roadmap (October 2024), the government announced plans to publish a consultation “to explore the tax treatment of predevelopment costs”. The consultation was postponed shortly after Ørsted’s ‘win’ in the Court of Appeal (in March 2025) but will, it is hoped, now proceed swiftly. The original aim of the consultation was to “encourage investment in renewable energy and major infrastructure projects” which the government consider a “core pillar of [its] Growth mission”. The consultation will provide businesses affected by this ruling with an early opportunity to explain the impact of drawing the “on the provision of” test so narrowly and help the government understand the importance of the capital allowance regime on major infrastructure investment and promoting long-term economic growth.