Poor weather has delayed the delivery of huge boulders that will form part of beefed-up sea defences aimed at protecting the storm-battered Torcross.
The boulders, ordered from quarries in Norway, Ireland and Scotland, were due to start arriving last week, however, inclement weather has delayed the arrival of the rocks that are being delivered by boat.
Some of the boulders are being delivered to Torcross by sea at high tide, with diggers then moving them into place at low tide. Some of the boulders will also be transported by road.
The Environment Agency confirmed that poor weather had “delayed the shipping company”.
“It is the company that makes the final call on whether or not to sail,” a spokesperson for the Environment Agency said.

Scaffolding adorns some properties in Torcross as repairs continue after dramatic storms damaged them earlier this year.(Image: Bradley Gerrard)
“We are expecting the first delivery of boulders on Friday (23 October), however, that might be delayed again due to poor weather.”
The spokesperson said deliveries were expected over a month-long period to provide the extra protection for the homes along the seafront in the South Devon village, which suffered a catalogue of damage during storms earlier in the year, including to homes and to a stretch of the main road to Dartmouth that was washed away.
Contractor Keir has commandeered the so-called Tank car park at Torcross, which is home to a General Sherman tank, with temporary offices and space for its plant vehicles – including a trio of huge diggers – that will be involved in the sea defence works.
These repairs do not, however, involve the A379 Slapton Line road, which is itself the subject of another £20 million bid to the government’s Structures Fund for cash to reinstate the highway.
In an update from Keir, sent to residents and businesses in the area, the firm welcomed the “high level of interest in the project”.
“The project team will be working to a vigorous programme, with complex shift patterns designed to make the most of the available tides and maximise the time available to undertake the marine works.
“This means that, at times, the team will be working through the night . Lighting will be used where required, with lights positioned to face away from the shore to minimise their impact on the surrounding area.”

Diggers and other machinery and temporary offices have taken over the so-called Tank car park at Torcross ahead of sea defence works.(Image: Bradley Gerrard)
It added a barge and two ships would be operating through to December to support the ongoing delivery and placement of rocks, subject to the weather conditions.
“This means there will be multiple opportunities over the coming months to see works progressing and capture some great views of the project – always from a safe distance,” it added, stating that during construction activities, the beach would be closed.
Separately, a host of properties damaged by storms earlier this year are still undergoing repairs as the major sea defence works are set to begin.
The range of works to properties includes repairs to walls, new windows, and internal refurbishment, with at least three homes with scaffolding on the outside to assist workers.
Some properties seem to have had debris removed that had been caused by the storm damage, but work on them appeared less obvious from the outside.