Siemens will build 30 Velaro Novo trains for Renfe, each with 520 seats in seven cars, at least 115 more than the eight-car Series 103, under a €1.218 billion award.
Rendering of a Siemens Velaro Novo high-speed train. Image: Siemens Mobility.
Spain’s state-owned operator announced the award to Siemens on October 27, 2026. The final price also covers the items needed to maintain the trains, and the deal includes an option for 10 more. The new sets are designed for a top speed of 350 km/h.
Velaro Novo seating compared with the Series 103
Renfe describes the Velaro Novo as a technical evolution of the Series 103, which Siemens also supplied. Renfe’s fleet data gives 404 or 405 seats per eight-car train for the 26-strong series, and the first of them was introduced on January 30, 2007. The new trains will add 115 or 116 seats with one car fewer. According to Renfe, technical equipment that is lighter and more compact than in its current high-speed fleet makes room for more seats while the train keeps the same length.
All 520 seats are on a single level. Turista, the standard class, has 404 seats, or 78% of the total, two on each side of the aisle. Preferente has 116 seats, or 22%, with two seats on one side and one on the other. Seats can be turned to face the direction of travel, and each one has a power outlet and a USB connection. Larger multipurpose areas will hold luggage, bicycles and passengers with reduced mobility.
Velaro Novo and Series 103 compared: at least 115 more seats per train with one car fewer
Per train
Velaro Novo (awarded October 27, 2026)
Series 103
Manufacturer
Siemens
Siemens
Cars
7
8
Seats
520 (404 Turista, 116 Preferente)
404 or 405 (Renfe lists both figures)
Design speed
350 km/h
350 km/h
Fleet size
30 trains, with an option for 10 more
26 trains
Timing
First five due within 40 months, all 30 within 62 months
First train introduced on January 30, 2007
Source
Renfe award announcement
Renfe Series 103 fleet page
Delivery schedule and tender terms
The first five trains are due within 40 months, with the rest following at an even pace until the order is complete within 62 months. Under the terms of the tender approved by Renfe’s board, the first five units were to join the fleet before month 40 and the entire fleet was to be fully operational before month 78. The tender also set a delivery rate of one train every month and a half. Renfe said it cannot afford a repeat of the delivery delays by manufacturers it experienced in recent purchases.
When it launched the tender, Renfe valued the 30 trains at €1.362 billion, or €1.777 billion if all 10 optional units were bought. The final award of €1.218 billion covers the 30 trains together with their maintenance items.
Renfe’s tender terms and the Siemens award compared
Term
Tender terms
Siemens award (October 27, 2026)
Price for 30 trains
€1.362 billion
€1.218 billion, including maintenance items
With 10 optional trains
€1.777 billion in total
Option for 10 more, price not stated
Seats per train
At least 450, in two classes
520, in two classes
First five trains
Join the fleet before month 40
Within 40 months
Full order
Whole fleet fully operational before month 78, one train every month and a half
All 30 within 62 months, at an even pace
Speed
350 km/h once infrastructure allows higher commercial speeds
Designed for 350 km/h
Notes
The tender announcement does not say whether maintenance items are part of the €1.362 billion figure.
Neither announcement gives the date from which the months are counted.
Source
Renfe tender announcement
Renfe award announcement
Renfe published the tender in April. Its award criteria included the manufacturer’s capacity and solvency to meet the committed delivery dates, along with a train able to run at 350 km/h. The tender announcement said the trains could operate at that speed once the infrastructure is ready for higher commercial speeds. The purchase is aimed mainly at renewing the trains with the most years in service. Renfe says it will both renew and enlarge its fleet to offer more seats and services in Spain’s liberalized high-speed market.
Velaro Novo technology and other orders
The design relies on fewer components, closer monitoring of onboard systems, advanced predictive maintenance and remote diagnostics to anticipate repairs and reduce breakdowns, cancellations and delays. A Last Mile system uses high-capacity batteries that can power the traction equipment and move the train after an incident. This reduces the immediate need for rescue locomotives. New bogies, lower weight and improved aerodynamics are intended to reduce noise, vibration and pressure waves in tunnels. The lighter design and new traction technology also cut energy use. A digital architecture supports higher-capacity Wi-Fi and system updates over the train’s service life.
Renfe also pointed to Siemens’ recent Velaro Novo work elsewhere. Siemens won a contract to supply 10 trains to VinSpeed in Vietnam, together with signaling, electrification and communications systems for the Hanoi–Quang Ninh and Ben Thanh–Can Gio lines. It was also selected to supply 10 trains to Brightline West for a new rail connection between Las Vegas and Southern California.