California High-Speed Rail’s board approved a Siemens Mobility contract capped at $772.1 million for three trainsets and maintenance, and environmentally cleared the last section of its 494-mile Phase 1 system.

Rendering of a Siemens American Pioneer 220 high-speed train in a preliminary California High-Speed Rail liveryRendering of a Siemens American Pioneer 220 trainset in a preliminary California High-Speed Rail livery. Image: Siemens Mobility / California High-Speed Rail Authority.

Directors took both actions at the authority’s Oct. 28–29 meeting in Anaheim. The authority’s announcement of the decisions links the trainset award to its target of passenger service by 2033, while the environmental vote leaves every project section between San Francisco and Los Angeles/Anaheim cleared.

What the $772.1 million contract covers

The $772.1 million is a not-to-exceed total for contract HSR23-18, divided into three parts in the staff memo to the board. A $281.7 million lump sum pays for manufacturing, delivering and commissioning the three trainsets. A second lump sum, $284.1 million, covers service mobilization, full service, spare parts and 10 years of maintenance. Up to $206.3 million more is set aside as provisional sums for escalation, foreign exchange, taxes and other items.

Import duties and tariffs sit outside that total. The board separately allowed up to $63.7 million for them, with staff estimating the charges at 20% of the trainsets’ cost. The award also lifts the program baseline and budget by $195.9 million to about $35.86 billion, because full service, spare parts and a decade of maintenance move from the operating plan into the capital plan. Funding comes from the authority’s commitment of Cap and Invest greenhouse gas reduction funds.

American Pioneer 220 trainsets built in Germany

The trainset presentation to the board identifies the model as the American Pioneer 220, the U.S. version of Siemens’ Velaro Novo. Each seven-car trainset is 664 feet long, has at least 450 seats in a 2+2 layout and is built for 220 mph. Two trainsets can run together as one 14-car train.

Final design, manufacturing and factory tests for the three initial trainsets will take place in Germany, with final testing and commissioning in California. Siemens was the only one of the two shortlisted teams, Alstom and Siemens, to submit a proposal, and it was confirmed as the apparent best value proposer after a best and final offer. The terms set out before the vote also showed how the order shrank from six initial trainsets in 2024 to three.

Testing on authority track from spring 2030

The board authorized the chief executive officer or a designee to sign the contract and issue notices to proceed 0 through 5, with the first two due one month after approval. On Oct. 29, directors named Joe Stephenshaw, director of the California Department of Finance, as interim chief executive officer.

After factory tests, shipping and import clearance, testing on authority track is scheduled to start in spring 2030. The August 2026 procurement revision requires the trainsets to be delivered and ready for dynamic testing in the Central Valley no later than February 2030, in line with the track and systems construction contract. The authority aims to have the Merced to Bakersfield Early Operating Segment running by 2033.

Siemens will maintain the trainsets for an initial 10 years from 2030, paid monthly against availability and reliability. The contract sets prices for up to 19 option trainsets, with price adjustments tied to published U.S. and German price indices, and service can be extended in five-year steps to as long as 30 years in total. Staff must return to the board before exercising any of those options.

Los Angeles to Anaheim section completes Phase 1 clearance

Before this vote, 463 miles of Phase 1 had environmental clearance. The board has now approved the final environmental document for the roughly 30-mile Los Angeles to Anaheim section, which runs from Los Angeles Union Station to the Anaheim Regional Transportation Intermodal Center through 12 cities in Los Angeles and Orange counties, the section presentation shows.

Phase 1 project sections and the year each was environmentally cleared

Project section
Environmental clearance

San Francisco to San Jose
2022

San Jose to Merced
2022

Merced to Bakersfield
2012 and 2014

Bakersfield to Palmdale
2021

Palmdale to Burbank
2024

Burbank to Los Angeles
2022

Los Angeles to Anaheim
2026, approved at the Oct. 28–29 board meeting

The first six sections made up the 463 miles cleared before the Oct. 28–29 meeting. The Los Angeles to Anaheim vote completes clearance for the 494-mile Phase 1 system. Merced to Bakersfield was cleared in two steps. Source: California High-Speed Rail Authority, Los Angeles to Anaheim board presentation, Oct. 28, 2026.

The route follows the existing LOSSAN rail corridor, where high-speed trains would share tracks with BNSF, Metrolink, Amtrak and LOSSAN services and run two trains per hour in each direction. The plan adds one mainline track along part of the corridor and electrifies two of the four mainline tracks.

In the Central Valley, over 90 miles of guideway and 70 major structures are finished, and 22 more structures are under construction across Madera, Fresno, Kings and Tulare counties.