Mercedes-Benz won’t start building the GLC compact SUV in Alabama until May 2030, about 30 months later than planned, according to Automotive News.

The trade paper’s report, published in early November, rests on two unnamed sources with knowledge of the schedule. Production at the Vance plant had been expected to begin in late 2027. The report concerns the next-generation GLC, not the current model, which arrived in 2022 and would be about eight years old by 2030.

Mercedes has given no reason for the change and has not confirmed the May 2030 date. A spokesperson gave a statement to Motor1, which asked about the report.

“At this time, we’re not providing an update on production timing or allocation of an individual future model. Our commitment to Tuscaloosa and our planned US investment of $7 billion through 2030 has not changed,” the spokesperson said.

Every GLC Sold in the US Is Still Imported

Automotive News put US sales of the GLC at almost 54,000 for January through September 2026.

None of those were built in America. The GLC comes from Europe, and passenger cars shipped from the European Union carry a 15% tariff under the current US-EU trade deal.

If the report is right, Mercedes will pay that duty on every GLC it sells here for about two and a half years longer than planned. The company hasn’t said how much that adds to its costs, or whether buyers will see any of it in sticker prices.

Rows of orange industrial robots welding a car body under bright lights on a long factory floorRobots in the body shop at Mercedes-Benz’s plant in Vance, Alabama, photographed in March 2026. The GLC is due to join the plant’s lineup. Image Credit: Mercedes-Benz

Mercedes Pledged $4 Billion for the Plant in March

The reported delay comes about seven months after Mercedes announced a $4 billion investment in the Vance plant through 2030, at a ceremony on March 31, 2026, marking the plant’s 5 millionth vehicle.

That money is part of more than $7 billion Mercedes plans to spend in the US. The Alabama Department of Commerce said in its release that the GLC was headed to the plant “in the next few years.”

The plant already builds the GLE, GLE Coupe and GLS, the electric EQE SUV and EQS SUV, and the Maybach versions of the GLS and EQS SUV. Mercedes chose Alabama for its first US factory in 1993, and the site launched the M-Class SUV in 1997.

The plant employs about 5,800 people and exports about 60% of what it builds. At the March ceremony, Mercedes board member Michael Schiebe, who oversees production, said the investment showed the company’s commitment to the site.

“We believe in Tuscaloosa. We are staying, we are growing, we are committed,” Schiebe said.