Kyon Energy said it has begun technical commissioning of its 100 MW/203 MWh battery in Dahlem, Germany, moving the project from construction into testing. Commercial operation is expected to start shortly.

The two grid connections at the substation built for the project were energized at high voltage in August. In the current “hot commissioning” phase, Kyon will test the plant’s electrical and control systems, how they work together, and its grid connection under a range of operating conditions.

Managing Director Thomas Maubert said the start of hot commissioning marks the decisive transition from construction to operation. He said all systems and components will now be tested step by step, with strict attention to occupational health and safety.

In December 2025, Kyon Energy and battery supplier Saft had scheduled energization for the second quarter of 2026 and commercial operation for October. The 70 lithium iron phosphate battery containers were installed in October 2025. Kyon did not give a reason for the delay.

Dahlem follows Kyon Energy’s projects in Arnsberg, Schobüll and Faid, and is the 11th project in the portfolio in which Allianz Global Investors bought its 50% stake this year.