The windfarm has a total of 64 Vestas V236-15.0 MW offshore wind turbines  and an installed capacity of 960 MW that makes it Germany’s largest offshore windfarm. It was built without state funding and is being financed solely through long-term power purchase agreements.

EnBW chairman Georg Stamatelopoulos said, “In recent years, we have invested billions in the expansion of renewable energy. He Dreiht is the largest single investment made by EnBW in renewables. It is also a perfect example of how renewable energy can prevail when the underlying conditions are right.

“We need more projects like He Dreiht, which deliver affordable, secure and clean electricity. At the same time, we have to gear Germany’s entire energy system toward these three aspects. And this will only be possible if we show courage combined with pragmatism.”

Federal Environment Minister Carsten Schneider said, “The He Dreiht windfarm sends a strong signal for the further expansion of renewables in our country. It will make us less dependent on fossil fuels. The development of offshore wind energy holds huge economic potential for coastal regions, but also for the whole of Germany as a business location. That is why it is so important to create solid political conditions for further environmentally compatible expansion.”

EnBW was awarded the contract for He Dreiht in 2017, in the first round of auctions for offshore windfarms in Germany, with no state funding. The company holds 50.1% off the shares through a project company. The remaining 49.9% are held by a consortium made up of Allianz Global Investors on behalf of Allianz entities, AIP Management and Norges Bank Investment Management. Around €2.4Bn is being invested in it.

Long-term power purchase agreements (PPAs) have been signed for electricity from the windfarm, giving companies long-term price stability and planning certainty while directly helping them to achieve their climate targets. Evonik, Google, the Telekom subsidiary PASM, Fraport, Bosch, Salzgitter, SHS Stahl-Holding Saar, Deutsche Bahn and DHL Group are among the contractual partners.

Construction work on He Dreiht got underway in May 2024. Network operator TenneT is responsible for connecting the wind farm to the electricity grid. The electricity reaches the coast via a platform in the sea and two submarine cables.

The task of transitioning He Dreiht into regular operation will be a gradual process that involves connecting the individual turbines to the grid one by one, testing them and starting them up. The first turbines are already feeding electricity into the grid, with the others set to follow. Based on current progress, the windfarm should be fully operational in the coming months.