German company Uniper Anlagenservice GmbH has become the first company to complete the dismantling, cutting up and packaging of two reactor vessels in waste containers within one year. The dismantling of Sweden’s Barsebäck 1 and Germany’s Neckarwestheim 1 was completed in December 2021.
Uniper Anlagenservice is a subsidiary of Uniper specialising in the dismantling of nuclear power plants. Because decommissioning a power plant involves a wide range of activities, the company typically draws on the expertise of other companies as well. Nukem Technologies was the main partner for the dismantling of Barsebäck, while at Neckarwestheim Uniper worked with GNS Gesellschaft für Nuklear and Westinghouse Electric Germany.
Uniper was selected to dismantle four units in Sweden: two at Barsebäck and two at Oskarshamn. The nuclear reactors at Barsebäck were shut down in 1999 and 2005.
The initial dismantling work was carried out in the turbine hall, where the power generation systems were dismantled. Work then moved to the plant’s primary circuit. Dismantling of the reactor vessel at Barsebäck’s first unit was completed in December last year. The entire operation took approximately one year.
Translation disclaimer
This article is a machine translation of the Czech original and has not yet been fully reviewed. In case of any doubt, please refer to the Czech version.