Uniper will invest about 120 million euros in the Bierwang underground storage facility to fill it 30% faster and reduce its emissions by 2030.

As announced by the German company Uniper on November 25, it will invest approximately €120 million in its Bierwang gas storage facility in Bavaria. The Bierwang2030 program will reduce the time required to fully fill the facility by 30%. It will also increase its maximum extraction capacity, allowing for earlier gas availability during the colder winter months.

A key gas storage facility for southern Germany

First, Uniper’s CEO, Michael Lewis, presented the program at the facility alongside Bavarian Minister-President Markus Söder. The new Bavarian Minister of Economic Affairs, Tobias Gotthardt, was also in attendance. The plant is located in the Mühldorf am Inn district, between Mühldorf and Wasserburg.

Bierwang, for its part, has been operating since 1975 and stores gas in sandstone layers at a depth of about 1,500 meters. Its usable gas volume is around 800 million cubic meters, equivalent to about 9 TWh. The facility can extract up to 1.2 million cubic meters of gas natural per hour.

The speed of extraction in winter

Regarding its function, on cold days both the stored volume and the speed at which it can be withdrawn are crucial. According to Uniper, the volume withdrawn in a single day would be enough to meet the demand of approximately three million single-family homes on an average winter day. For this reason, Bierwang is among the most powerful porous storage facilities in Germany.

Furthermore, the plant was operating at around 80% of its capacity at the end of November. This level exceeds that of seven other storage facilities crucial to Bavaria’s supply. Security of supply in the south of the country depends heavily on these underground reserves.

The measures of the Bierwang2030 program

The plan also combines construction work, technical upgrades, and organizational measures to expand capacity and increase the plant’s safety. Its centerpiece is a new 10-megawatt electric compressor unit, designed for potential future use with hydrogen. This equipment will replace two existing compressors powered by gas engines.

Likewise, storage capacity will increase by approximately 40 million cubic meters through the expansion of existing wells. According to the company, this amount of natural gas would supply about 20,000 single-family homes for a year. These investments strengthen the infrastructure of the midstream segment German.

Lower CO₂ and methane emissions

On the other hand, Uniper anticipates that the site’s annual CO₂ emissions will decrease by approximately 11,000 tons. Methane emissions are expected to fall by about 64 tons, thanks also to a recompression unit. This would reduce the plant’s emissions by more than half, and methane emissions from all of Uniper’s storage facilities would decrease by nearly 30%.

Similarly, the company highlights that it has consistently obtained OGMP 2.0 Gold Standard certification for methane management since it began submitting reports. This international standard evaluates the quality of emissions measurement and reporting in the gas sector.

Research with pure hydrogen

It is worth noting that Bierwang is home to the HyStorage research project, which studies hydrogen storage in porous rock formations. After four testing phases with mixtures of hydrogen and natural gas, the fifth phase now includes pure hydrogen. Preliminary results are promising, according to the company.

In this regard, the hydrogen will remain in a smaller, isolated storage facility for approximately three months. Its extraction is planned for January 2027, followed by a detailed analysis of the data. This line of work connects the plant to the European energy transition.

Going forward, Uniper will carry out the Bierwang2030 project to complete the modernization before 2030. HyStorage’s results in 2027 will determine whether German porous storage facilities can be adapted for hydrogen. Likewise, the company, currently owned by the German state, is preparing for its reprivatization with a €6 billion growth plan for projects through the beginning of the next decade.

Source and photo: Uniper