Green Volt, developed by Flotation Energy and Vårgrønn, signed a deal with Siemens Gamesa on November 24, 2026, to reserve manufacturing capacity for 28 turbines rated above 15 MW. The project is about 80 km from Peterhead, Scotland, and has consent for up to 560 MW

The Green Volt floating wind farm has reserved manufacturing capacity from Siemens Gamesa for 28 turbines, each rated above 15 MW.

The announcement was made Tuesday, November 24, 2026, in Aberdeen, Scotland.

The deal is outlined in the Green Volt announcement, published the same day. Offshore Engineer also reported the reservation on Tuesday, November 24.

The project is about 50 miles, or 80 km, from Peterhead and has consent for up to 560 MW.

Construction is expected to create more than 2,800 direct jobs and about 100 permanent operations positions.

In Brazil, offshore wind is still awaiting regulations. The first auction of offshore areas depends on a decree that Brazil’s Ministry of Mines and Energy plans to publish by the end of 2026.

What Siemens Gamesa reserved for Green Volt

The deal with Siemens Gamesa is worth several million pounds, though no exact figure has been disclosed. It secures manufacturing capacity and specialized engineering teams for the 28 turbines.

The developers say this is the first time anywhere in the world that a commercial-scale floating wind farm has reserved turbines of this size.

The move is still a reservation.

Darren Davidson, Siemens Energy’s director for the UK and Ireland, said important steps remain, but reserving capacity for 28 15-MW turbines is a concrete advance.

Davidson also noted that floating wind brings new opportunities and challenges, requiring close collaboration with suppliers.

He said Siemens would continue working with Green Volt through the remaining phases of the project.

Where the wind farm is located and how much power it could generate

Green Volt is in the North Sea, about 80 km from Peterhead, according to Ocean News. The Scottish government has granted consent for up to 560 MW of capacity.

The Siemens Gamesa turbines will float on structures anchored to the seabed. Water at the site is 90 to 100 meters deep, according to the project website.

The announcement says Green Volt is set to become the world’s largest commercial floating wind farm.

The power will go to the UK grid and help decarbonize offshore oil and gas platforms.

Flotation Energy presented the project in an English-language video published on YouTube on February 26, 2026. In it, the company’s chairman, Barry McLeod, discusses Green Volt.

McLeod says the partnership with Vårgrønn works because of shared values and an entrepreneurial spirit. In his view, delivering projects that are first of their kind worldwide depends on people, and the team was hand-picked.

Barry Macleod of Flotation Energy, Isla Robb of ETZ and Bob Sanguinetti of the Port of Aberdeen wearing hard hats on the dock, with ships and a rig in the background.Barry Macleod of Flotation Energy, Isla Robb of ETZ and Bob Sanguinetti of the Port of Aberdeen wearing hard hats on the dock, with ships and a rig in the background.Barry Macleod, Isla Robb and Bob Sanguinetti at South Harbour in Aberdeen, at the announcement of the agreement between Green Volt and the port. Photo: Green Volt.

Brazil’s offshore wind sector still awaits regulations and its first auction

Brazil has Law No. 15,097/2025, approved in January 2025, which governs offshore power generation. Regulations have yet to be issued.

On October 27, 2026, Cenário Energia reported that the Ministry of Mines and Energy plans to send a draft decree to the Office of the Chief of Staff, Brazil’s presidential office.

The goal is to publish the regulation by the end of 2026.

The decree is expected to address the allocation of offshore areas, Preliminary Interference Declarations and the stages for offering those areas.

Mariana Espécie, a secretary at the ministry, announced the plan at the Brazil WindPower event.

Tribuna do Norte reported in December 2025 that 104 offshore wind projects had applied for permits from Ibama, Brazil’s environmental agency, by March 2025. Fourteen are in Rio Grande do Norte.

In the same report, the ministry said there was still no forecast for an auction of offshore areas.

The only project to advance in Rio Grande do Norte is a test site run by Senai, Brazil’s National Service for Industrial Training, with a preliminary license for up to two experimental turbines.

Agreement with Port of Aberdeen includes £15 million

Green Volt also signed a letter of intent with the Port of Aberdeen. It calls for using South Harbour to prepare anchors and mooring lines for Siemens Gamesa’s turbines.

The agreement is expected to support a £15 million package of investment and spending on the port’s infrastructure, facilities and suppliers. Offshore Engineer converted the amount to US$19.6 million.

The package and economic benefits are subject to final confirmation, the statement said.

Bob Sanguinetti, chief executive of the Port of Aberdeen, said the £420 million investment in South Harbour puts the port at the center of Scotland’s offshore wind industry.

He said Flotation Energy wants to use the port to assemble and ship the Green Volt structures, citing its deepwater berths and large laydown area.

Sanguinetti expects the work to create business opportunities for suppliers in northeast Scotland. He also called for faster progress on the other projects from the ScotWind and INTOG rounds.

Jobs, investment and emissions cuts

Green Volt is expected to generate more than 2,800 direct construction jobs and about 100 permanent operating positions. The planned investment is about £2.5 billion.

The project website cites more than £1.3 billion in benefits to the UK economy. Once operational, the farm is expected to avoid about 1 million metric tons of CO₂ emissions a year.

The schedule calls for construction from 2025 to 2028, with first power expected in 2029.

Two wind turbines on yellow floating foundations in open water beneath a blue sky.Two wind turbines on yellow floating foundations in open water beneath a blue sky.Floating wind turbines in an image used by Green Volt to illustrate its target of delivering first power in 2029. Photo: Green Volt.
Who is developing the project and what has been approved

Green Volt is being developed by Aberdeen-based Flotation Energy and Norway’s Vårgrønn. In 2024, it received its main onshore and offshore permits.

That same year, it won a 400-MW Contract for Difference from the UK government. The contract guarantees a price for the farm’s electricity.

Energy Voice journalist Allister Thomas commented on the result in English on X on September 3, 2024, when the AR6 auction results were announced.

He wrote that Green Volt, set to become the world’s largest floating wind farm near Aberdeen, was among the winners. He also said only 5 GW of wind power was awarded in the round.

CfD results from the AR6 round are out.

Green Volt, to become the world’s largest floating wind farm off #Aberdeen, is among the winners.

However, only 5GW of wind power awarded this round, so hitting 2030 Gov target of 50+ GW looks v challenging
#OffshoreWind pic.twitter.com/apfTwA3rvb

— Allister Thomas (@AllisterMThomas) September 3, 2024

The project faced turbulence in 2026. Energy Voice TV published an English-language program about the North Sea on YouTube on October 15, 2026.

The video’s description says Flotation Energy confirmed staff cuts. This came amid rumors that Vårgrønn was planning to leave Green Volt.

Kincardine, Flotation Energy’s earlier experience

Flotation Energy’s founders played a central role in the Kincardine floating wind farm. It is located 15 km off the coast of Aberdeen.

The company calls Kincardine the world’s largest grid-connected floating wind project. The video below, in English, was published by Flotation Energy on YouTube on May 14, 2025.

The footage shows the floating structures being towed to the wind farm site off the coast of Scotland.

What companies and governments said

Matt Green, Green Volt project director, called the two agreements milestones for floating wind. “Reserving turbines of this size is unprecedented anywhere in the world,” he said.

He said the agreements bring the project closer to construction and should attract new contracts. Green said the company will explore manufacturing opportunities in the UK with Siemens Gamesa.

UK Energy Minister Michael Shanks said the announcement was a vote of confidence in Scotland’s industrial future.

Stephen Gethins, Scotland’s energy minister, said the country is recognized as a global leader in floating wind. Isla Robb of ETZ Ltd called the announcement a milestone for Scottish industry.

Robb said Aberdeen and northeast Scotland are well positioned to lead the sector, thanks to their energy expertise, suppliers and investment in the port.

What still needs to happen before construction can begin

Green Volt still needs to secure other major contracts and attract more investment, according to Offshore Engineer.

The reservation with Siemens Gamesa and the letter with the port prepare the project for this stage, but they are not yet firm supply contracts.