A view of an access road to the construction site of the insolvent battery manufacturer Northvolt. Marcus Brandt/dpa
The insolvency of Swedish battery maker Northvolt will cost German taxpayers less than previously estimated, after parts of public funding were recovered, officials said on Friday.
As part of US firm Lyten’s planned acquisition of Northvolt’s German subsidiary, the Northvolt Drei gigafactory project, the federal government and the northern state of Schleswig-Holstein have recovered €153 million ($179.2 million) in public funds.
The money has already been repaid, the German Economy Ministry confirmed to dpa. The sum will be split equally between the federal and state governments.
In addition, up to €69 million could flow back to the state development bank KfW this summer as part of a solvent liquidation of the Northvolt Drei project, pending final approval of the site’s emissions permit.
The ministry said recovering taxpayer money had been a priority from the start.
Northvolt had planned to build a large battery factory in Germany and received a €600 million loan package from KfW, backed equally by Berlin and the Schleswig-Holstein state government.
About €330 million was spent on construction, land and equipment. Nearly €50 million remains in a blocked account but is already earmarked to support the German subsidiary.
Berlin used a restructuring procedure under German law to stabilize the project, as the German subsidiary was not insolvent, unlike Northvolt’s Swedish parent company.
Courts have approved the restructuring plan, the ministry said.
More money could still be recovered if battery technology firm Lyten completes its takeover.
The company plans to acquire both the German subsidiary and Northvolt’s Swedish parent company. Talks with German authorities and KfW are ongoing.
Lyten said it initially plans to create around 1,000 jobs at the Heide site north of Hamburg, where it intends to produce batteries for defence, energy storage, mobility and electric vehicles.
Dan Cook, CEO of US company Lyten, speaks during a press conference in front of the State Chancellery in connection with discussions about the company’s planned factory near Heide in Dithmarschen. The Swedish company Northvolt had previously planned to build a battery factory in the region expected to create around 3,000 jobs. Frank Molter/dpa