Check out five upcoming, ongoing and completed transportation projects around Dallas-Fort Worth.
This list is not comprehensive.
Upcoming projects
Project: Prosper Trail will undergo a full pavement reconstruction from Coit Road to Custer Road. The new pavement section will be a four-lane concrete divided roadway.
Update: The design phase is nearing completion, and construction is expected to begin in summer 2028.
Timeline: summer 2028-summer 2029Cost: $13.45 millionFunding source: town of Prosper
2. Stonebridge Drive extension
Project: Crews will construct two lanes of Stonebridge Drive between US 380 and Bloomdale Road. A full six-lane bridge will be constructed over Wilson Creek.
Update: The preliminary alignment study is nearly complete. A final design contract is expected to be presented to McKinney City Council for approval in fall 2026.
Timeline: Final design is expected to begin in fall 2026. Construction is expected to begin in 2028.Cost: $35 millionFunding source: city of McKinney
Ongoing projects
3. West Continental Boulevard intersection improvements
Project: Construction is ongoing for the second of four phases for improvements along West Continental Boulevard in Southlake. Improvements included within the second phase are expected to improve the traffic flow within the area.
Update: Crews shifted traffic near the intersection of Continental Boulevard and Davis Boulevard on July 20, according to a city update. The contractor has started work on the north side of Continental Boulevard, and traffic has been moved to the newly paved south portion of the roadway.
Timeline: April 2026-February 2027 (Phase 2)Cost: $15.3 million (phases 1-4)Funding source: city of Southlake
Project: Lebanon Road is being widened from a four-lane roadway to a six-lane roadway in Frisco. The project spans from FM 423 to Todd Drive, which is just west of Legacy Drive.
Update: The project is under construction and expected to be completed next year.
Timeline: mid-2025-late 2027Cost: $23 millionFunding source: city of Frisco, Denton County
Completed projects
5. Sunset Street utility installations
Project: Sunset Street between Carroll Boulevard and Bolivar Street received a new waterline and total pavement replacement as part of the Neighborhood 2 bond package approved by voters in 2019.
Update: Utility installations and road repairs are complete. The road reopened in April, and final work items were completed in June.