Tokyo Gas Engineering Solutions (TGES), a subsidiary of Tokyo Gas, Nippon Paper Industries, and Getworks, which operates container-type data centers, announced on the 5th that they will build a data center at the site of Nippon Paper Industries’ former Kushiro Mill in Kushiro, Hokkaido, Japan. Operations are set to begin at 6 megawatts by March 2027, with a vision to eventually expand to 150 megawatts.

In the three-company joint project, TGES will oversee the overall business, Nippon Paper Industries will provide land and power, and Getworks will install container-type facilities. Project costs were not disclosed. Descriptions of the launch timing and expansion plans differ in detail across the announcement materials, and the phased expansion roadmap is expected to require further scrutiny.

Nippon Paper Industries’ Kushiro Mill has a site of approximately 800,000 square meters and ended paper production in 2021. While repurposing the site has been a challenge, the mill continues to operate a coal-fired power generation business, and this power will be supplied to the data center. TGES began studying a project in Kushiro in May 2026 and formed a business alliance with Getworks in September of the same year. The Kushiro project is the first initiative since the alliance.

The three companies released a statement saying, “In Kushiro, which has an advantage in data center cooling thanks to its cool climate, we will contribute to the formation of a new industrial base.”

ItemDetailsLocationFormer Nippon Paper Industries Kushiro Mill site (Kushiro, Hokkaido)Initial operation6 megawatts by March 2027Expansion planUp to 150 megawattsMain rolesTGES = project oversight; Nippon Paper Industries = land and power supply; Getworks = container-type facilitiesPower sourceCoal-fired generation at the same site

Note: Because descriptions of the launch timing and expansion scale vary across the announcements, only the initial operation and maximum scale are listed.

As securing power for data centers becomes an industry-wide challenge, the three companies position the site—which combines existing power generation infrastructure with a cool climate—as advantageous in terms of both cooling costs and power procurement. TGES has a sales office in Sapporo and operates engineering businesses across Hokkaido, including a combined heat and power system at the Meiji Tokachi Plant (Memuro, Hokkaido), and in the expansion phase in Kushiro it plans to consider using distributed power sources such as gas-fired generation equipment.

The move to convert idle industrial zones in regional areas into digital infrastructure is drawing attention as a case that simultaneously advances the effective use of power and land and the renewal of local industry. On the other hand, supplying power derived from coal-fired generation to a large-scale data center may raise questions about reviewing the future power mix from a decarbonization perspective.