Elon Musk’s massive semiconductor production project “Terafab,” pursued through Tesla and SpaceX, has begun placing concrete orders with Japanese equipment makers. It is moving up equipment procurement schedules to meet a target of starting mass production in the second half of 2028, but the industry is uneasy about the aggressive timeline set by Musk, who has no semiconductor manufacturing experience.
According to Nikkei on the 9th, several Terafab procurement officials visited Japan earlier this month and held meetings with local semiconductor equipment suppliers. They reportedly asked some companies to supply equipment with delivery dates just a few months away. The effort is aimed at aligning equipment procurement with the second-half 2028 mass production target Musk presented last month.
Terafab is a semiconductor production project jointly pursued by Tesla and SpaceX in the U.S. state of Texas. Its purpose is to secure, without relying on outside suppliers, the chips needed for self-driving cars, the humanoid robot Optimus, and the space AI data centers SpaceX is envisioning. Musk judges that even if existing suppliers such as Samsung Electronics and TSMC expand production, they will struggle to cover the volumes he will need. When he unveiled the Terafab concept in March, he said the pace of capacity expansion by partners fell short of what he wanted. His vision is to bring design, manufacturing, packaging and testing together in one place to accelerate semiconductor development and production.
The long-term production target is 1 million wafers a month. Terafab has informally told equipment makers and others this fall that it aims to reach that scale of mass production after 2032. Of that, about 700,000 wafers are to be allocated to memory chips for data storage and more than 300,000 to logic chips for computing. The memory target alone is on par with Samsung Electronics’ total DRAM capacity of 650,000 to 700,000 wafers a month. That is 40 times the 25,000-wafer monthly capacity planned by Japan’s Rapidus at its Chitose plant in Hokkaido.
CategoryTerafab target (after 2032)ComparisonMonthly capacity1 million wafers40 times Rapidus’ 25,000 wafers at ChitoseMemory700,000 wafersSamsung Electronics’ total DRAM of 650,000–700,000Logic (computing)More than 300,000 wafers-Phase 1 investment$16.8 billionGrimes County, Texas
When the concept was announced in March, there was considerable skepticism in the industry. It was hard to gauge how seriously Musk would enter the semiconductor industry, which requires specialized manufacturing experience. But as concrete orders begin to move, more companies are treating them as real business opportunities. “The biggest topic in the semiconductor industry right now isn’t Kioxia or Rapidus. It’s Elon Musk,” one supplier executive said.
The push to secure equipment began even before the Japan visit. In SpaceX’s earnings presentation on the 20th of last month, Musk thanked ASML and its partners for moving up equipment delivery dates. He is also pressing Japanese companies for fast delivery. An official at one equipment maker said Terafab set delivery dates just a few months out, adding, “It’s an unreasonable order, but we have no choice but to respond as much as we can.”
The key question is what happens after the equipment is secured. Cutting-edge semiconductor plants typically take more than three years from construction planning to mass production. Even after equipment is installed, considerable time is needed to lower defect rates and achieve stable output. Terafab has chosen to verify technology at a research facility in Austin and then scale up to the large production site in Grimes County. Musk has said he aims to have the first test chips working properly at the research facility in May or June of next year and to enter mass production in the second half of 2028. He himself has called the schedule “very aggressive.”
Terafab has also joined hands with Intel to secure manufacturing technology. Intel announced in April that it would cooperate with Terafab on chip design, manufacturing and packaging. Terafab plans to use Intel’s 14A process for logic chips. Cooperation with TSMC is also under discussion, but the specific form of participation has not been finalized. After Musk described TSMC as a “subcontractor,” the two sides are said to be negotiating remaining issues such as operational control and investment size. Musk has ruled out allowing the Taiwanese company to hold a stake in Terafab or operate its plants.
Whether the massive investment can be recouped is another challenge. The Texas state government said Phase 1 investment in Grimes County alone amounts to $16.8 billion. Hisaya Suzuki of market research firm Omdia noted, “With demand for SpaceX chips unclear, we need to watch whether the plant can smoothly fill its capacity even after completion.”
Terafab’s moves are expected to affect the order landscape of the global semiconductor equipment market. Japanese equipment makers welcome the emergence of a major customer but appear torn between tight delivery deadlines and an unproven mass production schedule. If the goal of securing memory capacity equivalent to Samsung Electronics’ entire output by 2032 becomes reality, some observers say it could act as a long-term variable in global memory supply and pricing.