LONGVIEW, Wash. (KATU) — Washington officials announced Friday they would be fining Nippon Dynawave over $10 million for safety and environmental violations after an investigation into the chemical tank collapse at its pulp mill in southwest Washington killed 11 workers.
The incident at the Nippon Dynawave facility in Longview on May 26 is one of the deadliest U.S. workplace accidents in decades.
State inspectors had planned to visit the plant to interview workers about two unrelated safety complaints the week of the tragedy. Those plans were disrupted when the white liquor tank failed, expelling huge amounts of the caustic liquids.
READ MORE | Records reveal safety complaints, poor maintenance at site of deadly Nippon tank collapse
In its investigation, Washington State Department of Labor & Industries said it reviewed more than 40,000 documents and interviewed more than 70 witnesses. The agency said its findings show the company knew the tank walls were too thin and did not act on repeated warnings.
L&I said Nippon kept operating G-tank for 43 weeks after a July 2025 consultant report said the tank was not fit for continued service and had a high likelihood of failure. The agency said the company did not repair the tank, reduce its capacity or take it out of service.
“Our citations include egregious, willful, serious violations for keeping G-tank in operation despite repeated notice that it was not fit for service,” said Director Joel Sacks of the Washington State Department of Labor & Industries. “This is our next step in the pursuit to prevent [this tragedy] from happening again.”
Dan Pitts, the agency’s director of statewide compliance, said the tank should have been repaired, its capacity reduced or it should have been taken out of service.
“Repair it, reduce the pressure on the walls by limiting how much liquid goes in or take it out of service,” Pitts said.
Pitts said the company instead kept operating.
L&I said it will refer the case to prosecutors for possible criminal prosecution.
They also discussed the citations and violations they would be issuing to Nippon Dynawave. You can watch a news conference from officials below:
The departments announced that Nippon Dynawave is facing a combined $10,138,127 in penalties for violations of state health, safety, and environmental regulations.
The Department of Labor & Industries said it is citing the company for 75 violations and imposed a fine of $9.1 million. The Department of Ecology is fining the company $960,000 in environmental penalties, as well as cost recovery for the emergency response.
KATU News reached out to Nippon Dynawave for a response to the state departments’ investigations, including asking why they continued to operate with the G-tank despite inspections finding it was not fit for service months before the rupture. You can find their response below:
Nippon Dynawave Packaging has cooperated with L&I throughout its investigation. We are now reviewing its findings in detail. The report’s characterization of NDP’s actions as “egregious and willful serious” failed to include important facts and context regarding actions taken by NDP and the timeline of events leading up to and on the day of the May 26th incident. We will address that issue through the appropriate appeals process.
We are also reviewing Ecology’s penalty and the anticipated cost recovery request in detail, including the basis for each, before determining next steps.
We are committed to establishing a complete and accurate account of the May 26 incident to help prevent future tragedies. It is important to distinguish between the workplace safety findings in L&I’s report and a determination of what caused the May 26 incident. The report does not establish root cause, which remains under investigation.
We will continue to cooperate with the appropriate agencies. We believe the responsible course is to allow the full investigative process to proceed and establish a complete and accurate record before conclusions are reached. Because the investigation remains ongoing, we will not provide further comment.
Previous findings
Federal investigators from the U.S. Chemical Safety and Hazard Investigation Board (CSB) previously said Nippon Dynawave kept using the storage tank for months after an inspection found it was too thin in places to safely remain in service and warned of a high likelihood of failure.
PAST REPORTING | Nippon tank was unfit for service 10 months before implosion, federal report says
An inspection contractor hired by Nippon Dynawave examined the 1.2 million-gallon G Tank in July 2025. The inspection found significant thinning in the lower portions of the tank, including areas below the minimum safe wall thickness, according to the CSB.
The contractor recommended Nippon Dynawave conduct an internal inspection and repair the tank’s first three shell sections. Its report said the tank was “not fit for continued service” without repairs and identified a high likelihood and consequence of failure.
Timeline of the collapse
The CSB looked into the events of the collapse, and found that a process upset occurred in the mill’s digestor unit at 1:55 a.m. on May 26.
White liquor flow from G Tank to the digestor slowed before stopping completely around 4:08 a.m., and white liquor continued flowing into the tank at a reduced rate, causing its level to rise.
By 6:22 a.m., investigators said the tank was about 90% full. Employees began reporting to work around 7 a.m.
At 7:09 a.m., G Tank catastrophically failed, releasing roughly 900,000 gallons of white liquor.
The release sent a large wave through the mill courtyard, damaging vehicles and parts of nearby buildings. Several workers attempted to escape.
The CSB also said a radio call went out for Nippon Dynawave’s medical emergency response team but did not indicate that white liquor had been released.