The renewable energy data centre in Hokkaido’s Ishikari (Image: Daibiru)
Japanese office landlords Daibiru and Sankei Building are joining Osaka Gas Urban Development in taking stakes in a renewable-powered, 15-megawatt data centre in Hokkaido developed by Tokyu Land and Flower Communications, according to announcements by the companies.
The three are investing in Ishikari Renewable Energy Data Center No.1, with Daibiru and Sankei Building expecting to complete their investments on 31 March 2027. The companies gave no financial terms. Daibiru, a wholly owned subsidiary of shipping group Mitsui OSK Lines, is making its first-ever data centre investment, while Sankei Building opened its first facility, Optage Sonezaki Data Center in Osaka’s Higashi-Umeda district, in 2025.
Daibiru is branching out from an office portfolio concentrated in Osaka and Tokyo. The investment is part of the group’s long-term plan to expand investment in Japan and overseas.
In a release late last week, the company said it aimed to “capture new business opportunities in this growth sector and build up its expertise in the data centre business.”
Powered in Ishikari
The 10,065 square metre (108,338 square foot) facility in the Ishikari Bay New Port area has 15MW of incoming power capacity. Construction finished on 27 March and the centre began service on 1 August. Tokyu Land and Flower Communications managed development for the project company, with Agility Asset Advisers serving as asset manager.

Daibiru president and CEO Hirofumi Kuwata (Image: Daibiru)
The facility draws all its electricity from renewable generation in Ishikari, a city on Hokkaido’s western coast facing Ishikari Bay and the Sea of Japan. Tokyu Land and the city have used private power lines to deliver locally generated electricity directly under a power purchase agreement, while Hokkaido’s mild climate can help reduce demand for mechanical cooling.
GMO Internet plans to open a site for its GPU cloud service by year-end in part of a data hall operated by BroadBand Tower. The service supplies computing power for AI workloads, including training and running large language models.
Tokyu Land and its partners cited difficulty securing additional power in the Tokyo area as a reason for choosing Ishikari. They also pointed to the value of putting computing capacity far enough from the capital to help keep services running if a disaster disrupts the Tokyo region.
About 90 percent of Japan’s data centres are concentrated in Greater Tokyo and Greater Osaka, according to JLL. The consultancy expects new supply in both established clusters and emerging locations as rising AI use adds pressure on power supplies.
Big Deals, New Chip Risks
Greater Tokyo’s operating data centre capacity rose 18 percent year-on-year to 1,397 megawatts in the first half of 2026, even as vacancy fell to 4.4 percent, according to Cushman & Wakefield. Data centre research firm DC Byte said in June that constraints on land and power in Tokyo were drawing developers to Osaka and prompting interest in markets farther afield, including Kyushu.
Greater Osaka was home to Asia Pacific’s largest transaction of a single data centre in the first nine months of 2026, with MSCI recording $992.1 million for the Colt DCS Keihanna facility. CapitaLand Ascendas REIT paid S$620.7 million ($460 million) for its 49 percent stake in the property alongside a fund managed by Mitsui & Co Realty Management. The asset was the first development under a fund backed by the Canada Pension Plan Investment Board.
Greater Tokyo also drew one of the year’s biggest investments. Keppel DC REIT and its sponsor agreed in September to acquire a 90 percent interest in two hyperscale facilities in Inzai from a venture of GIC and Equinix, in a deal valuing the properties and their operating company at JPY 190 billion ($1.2 billion).
The expansion has come with setbacks. Shares in Tokyo-listed AI infrastructure provider Datasection dropped 43 percent over three sessions last week after the company cut its annual revenue forecast by 89 percent to JPY 17.3 billion. Datasection cited a major computing contract cancelled in August and delays in bringing data centres online.
The Financial Times reported last December that Chinese tech giant Tencent was the end customer behind more than $1.2 billion in Datasection contracts, citing people familiar with the matter.
New US rules took effect last Thursday after Nvidia announced co-founder Jensen Huang’s resignation as CEO amid scrutiny of chip sales to Singapore’s Megaspeed. The rules add licensing requirements for shipments of advanced chips to four Southeast Asian countries and Brazil. They also reach data centres that supply significant amounts of computing power to certain customers in China and other restricted markets, including through intermediaries.