POSCO Group Chairman Chang In-hwa (sixth from right) poses for a photo with Karina Milei (seventh from right), chief of staff of Argentina's presidential office, and others at the completion ceremony for the upstream process of the second brine lithium plant held near the Hombre Muerto salt lake in Argentina on Dec. 6, local time. Photo courtesy of POSCO Holdings - Seoul Economic Daily Finance News from South KoreaPOSCO Group Chairman Chang In-hwa (sixth from right) poses for a photo with Karina Milei (seventh from right), chief of staff of Argentina’s presidential office, and others at the completion ceremony for the upstream process of the second brine lithium plant held near the Hombre Muerto salt lake in Argentina on Dec. 6, local time. Photo courtesy of POSCO Holdings

POSCO Group Chairman Chang In-hwa returned to the high-altitude salt flats of Argentina on the opposite side of the globe, 20 months after his February 2025 visit, to mark the completion of upstream facilities at the group’s second lithium plant at the Hombre Muerto salt lake. The company plans to press ahead with the downstream section of the second plant, due for completion next year, as well as with investment in third and fourth plants, keeping on schedule to build a 100,000-ton brine lithium production system by 2033.

POSCO Holdings said on the 7th that it held a completion ceremony for the upstream section of its second brine lithium plant near the Hombre Muerto salt lake in Argentina on the 6th, local time. Attendees included Chang, POSCO Argentina head Park Hyun, Korean Ambassador to Argentina Lee Jong-hwa, Argentine Presidential Chief of Staff Karina Milei and Argentine Cabinet Chief Diego Santilli. Karina Milei is the sister of Argentine President Javier Milei and is considered a central figure in the current administration.

The upstream section of the second plant, built with a total investment of $954 million, has an annual production capacity of 23,000 tons of lithium carbonate. Linking that output to the downstream section scheduled for completion next year at the Yulchon Industrial Complex in South Jeolla Province, where it will be converted into 25,000 tons a year of battery-grade lithium hydroxide, will complete a brine-based lithium hydroxide production system totaling 50,000 tons. Brine lithium, extracted by evaporating water from salt water, is first converted into lithium carbonate before additional processing turns it into lithium hydroxide. The 50,000 tons of high-purity, highly reactive, high-value lithium hydroxide is enough for about 1.25 million electric vehicles.

POSCO Group began developing its own lithium extraction technology in 2010 after identifying the metal’s growth potential, and continued making early investments, including acquiring mining rights to the Hombre Muerto salt lake in Argentina in 2018. Those efforts bore fruit in 2024, when it completed its first plant with annual capacity of 25,000 tons and started commercial production. The operation recently turned a profit for the first time.

In July, POSCO Argentina became the first Korean company to win approval under RIGI, the Argentine government’s large-scale investment incentive program, securing benefits including a lower corporate tax rate and tariff exemptions. In August, it won approval for a $700 million short-term credit line from IDB Invest, establishing a stable base for operating funds. The project is moving ahead smoothly with strong support from the local government.

POSCO Holdings will accelerate investment in the third and fourth plants, aiming to complete a 100,000-ton brine lithium production system by 2033. Each of the two plants will have annual lithium carbonate capacity of 25,000 tons, positioning the company to respond to growth in the energy storage system market driven by the spread of AI data centers and to rising demand for lithium iron phosphate batteries. The strategy is to build a balanced product portfolio spanning both lithium hydroxide and lithium carbonate. POSCO Argentina took its first step on the day of the ceremony by signing a memorandum of understanding with the provincial governments of Salta and Catamarca to advance the third and fourth plants.

“I have been visiting sites in person to find salt lakes suitable for lithium development since my time as head of new business in 2014, and reaching completion today after overcoming countless obstacles in the extreme environment at 4,000 meters above sea level is deeply moving,” Chang said. “This completion brings POSCO Group a step closer to becoming a resource development company that represents South Korea.” He added, “We will continue to secure competitive resources ahead of others, connect them to production and earnings, and reliably supply the critical minerals our national industry needs.”

Under its Triple-Core strategy of building industrial resources, strategic resources and energy resources into core growth pillars, POSCO Group plans to strengthen competitiveness across the chain from resource acquisition to development, production and earnings, aiming to emerge as South Korea’s leading resource development company and contribute to stabilizing the national critical minerals supply chain.

Park Hyun (front row), head of POSCO Argentina, signs a memorandum of understanding (MOU) with the provincial governments of Salta and Catamarca on Dec. 6, local time, to pursue the third and fourth plants, as POSCO Group Chairman Chang In-hwa (back row, from left), Argentine Federal Chief of Staff Diego Santilli, Argentine presidential chief of staff Karina Milei and Lee Jong-hwa, South Korean ambassador to Argentina, pose for a photo. - Seoul Economic Daily Finance News from South KoreaPark Hyun (front row), head of POSCO Argentina, signs a memorandum of understanding (MOU) with the provincial governments of Salta and Catamarca on Dec. 6, local time, to pursue the third and fourth plants, as POSCO Group Chairman Chang In-hwa (back row, from left), Argentine Federal Chief of Staff Diego Santilli, Argentine presidential chief of staff Karina Milei and Lee Jong-hwa, South Korean ambassador to Argentina, pose for a photo.