KT Cloud is building a 50-megawatt (MW) artificial intelligence-dedicated data center in Ansan, Gyeonggi Province, South Korea. The company said on the 22nd that it has begun construction on the Ansan AI data center (AIDC). Completion is targeted for 2029.

The project is part of KT Cloud’s mid- to long-term strategy to secure 1 gigawatt (GW) of AIDC supply capacity by 2031. The company plans to sequentially secure new sites, including Ansan, to expand the base for supplying AI infrastructure in the Seoul metropolitan area.

The Ansan AIDC will be built with about 36,878 square meters of gross floor area across two basement levels and nine above-ground floors. It is a hyperscale-class AI-dedicated facility with total power receiving capacity of 50MW, to be built on company-owned land.

From the design stage, the facility was planned around high-density, high-heat AI servers. All server rooms are designed to accommodate liquid cooling, allowing efficient handling of the heat that grows as computing performance rises. It marks an additional expansion of liquid-cooling infrastructure following the data center in Gasan-dong, Seoul, which opened last year.

The building structure is also reinforced with the introduction of next-generation GPUs in mind. Server room floors and the building structure were designed with a high-load approach to bear the weight of high-performance equipment such as Nvidia’s next-generation AI GPU “Vera Rubin.” The aim is to respond flexibly even if server density increases or equipment specifications change in the future.

A pre-cooling system will also be introduced to raise cooling energy efficiency. Cooling coils will be installed on the exterior walls to use natural wind at the upper part of the building, and these will be connected to closed-type cooling towers. The method uses the low outside-air temperatures of the shoulder seasons and winter for cooling, reducing the operational burden on cooling tower fans and chillers.

CategoryDetailsLocationAnsan, Gyeonggi Province, South KoreaTotal power receiving capacity50MWGross floor areaAbout 36,878 square metersScaleTwo basement levels, nine above-ground floorsCompletion target2029Cooling methodLiquid cooling support in all server rooms, pre-cooling systemBuilding structureHigh-load design (to accommodate high-performance GPUs such as Nvidia Vera Rubin)

Kim Bong-kyun, CEO of KT Cloud, said, “The Ansan AIDC is a project that reflects power and cooling infrastructure optimized for high-density AI servers and next-generation design technology.” He added, “Based on our accumulated data center construction and operation experience and in-house technical capabilities, we will provide stable and efficient AI infrastructure and actively respond to customers’ diverse technology needs.”

For AI data centers, power and cooling effectively determine competitiveness. The more GPUs are densely packed, the more heat density soars, making air cooling difficult to handle, and the power system must also be designed on the premise of large-capacity power receiving. KT Cloud’s decision to put liquid cooling and high-load structures at the forefront is aimed at these changes in the operating environment.

The market expects competition to expand AI infrastructure, centered on the Seoul metropolitan area, to intensify further. With domestic platform companies such as Naver and Kakao and global cloud operators unveiling AI-dedicated facility investment plans one after another, securing a single 50MW-class site is seen as a foundation for attracting large customers. However, stably managing power approvals and the construction schedule through the 2029 completion date is cited as a key challenge.