Steam rises from the cooling towers of the Dukovany nuclear power plant near the village of Dukovany, Czech Republic, on May 12, 2025. The plant is operated by Czech utility CEZ. Yonhap News
Team Korea, the consortium that won the 27 trillion won Dukovany nuclear power project in the Czech Republic, has broken apart in talks over the construction contract. Korea Hydro & Nuclear Power says it will look for a new builder after failing to close a price gap of more than 1 trillion won, while Daewoo Engineering & Construction counters that excessive costs and liabilities were pushed onto a builder that had no role in the design work.
KHNP said on the 29th that it had ended construction contract negotiations with the consortium of Daewoo Engineering & Construction and Doosan Enerbility. Since signing the main contract with the Czech client in June last year, the two sides held 78 working-level meetings, 11 dispute mediation committee sessions and two meetings between chief executives over roughly 15 months without reaching agreement, KHNP said.
The Dukovany project calls for building two 1,000-megawatt Korean-designed APR1000 reactors in the Czech Republic. Contracts for comprehensive design services by KEPCO Engineering & Construction and for the supply of reactor equipment and turbine generators by Doosan Enerbility have been signed, but the construction contract was never completed. KHNP plans to hold a briefing for potential builders in January, issue a tender notice in April and sign a contract with a new builder by July.
The central obstacle was the question of who pays when construction volumes grow as the design becomes more detailed. KHNP’s position is that the total construction cost must be fixed based on volumes at the time the basic design is approved. Daewoo Engineering & Construction, by contrast, demanded settlement for volumes that increase after the detailed design stage.
KHNP said that because its contract with the Czech client, EDU II, is on a fixed-price basis, signing the construction contract alone on a later-settlement basis would leave KHNP absorbing the added costs. It said it had offered an adjusted proposal that raised the baseline volumes and allowed actual-cost settlement for some works in order to reduce the builder’s burden, but that no agreement was reached. KHNP said the price gap between the two sides exceeded 1 trillion won, adding that “the scale was unacceptable, so we decided to terminate the contract talks.”
Daewoo Engineering & Construction countered that the problem was not primarily about asking for more money but about contract terms that required the builder to bear risks beyond its control. The APR1000, being built commercially for the first time, carries large volume volatility driven by design, it said, while the design is performed by KEPCO Engineering & Construction and the builder simply constructs according to the drawings. Daewoo Engineering & Construction said KHNP sought to place on the builder both responsibility for failing to detect design errors and matters whose scope of work was undefined.
The two sides also gave conflicting accounts of whether risk-related costs were included in the bid price. KHNP said bidders were instructed to price in risks such as volume increases at the time of the initial tender. Daewoo Engineering & Construction rejected that, saying KHNP “officially requested that contingency reserves not be included in the builder’s estimate because KHNP would apply them collectively,” adding that “we therefore excluded the reserves and stated so in the estimate calculation documents.”
Whether additional construction costs were reflected is another point of contention. KHNP said it had incorporated into the construction cost work items identified after the tender, but Daewoo Engineering & Construction said the “increase for the additional work amounted to less than 40% of the actual estimated amount.” It said KHNP presented higher construction volumes while demanding lower unit prices so that the overall contract amount would stay in line.
The differences between the two sides date back to the period when the project expanded from one reactor to two. According to KHNP, the consortium selected in 2018 agreed on the price for a single reactor, Dukovany Unit 5, and on fixed-price terms at the initial tender in 2022 and the revised tender in 2023. But no agreement was reached for the final tender in April 2024 covering two reactors, Units 5 and 6, and KHNP submitted its bid using figures it calculated on its own.
Daewoo Engineering & Construction said that during the negotiations it had gone as far as submitting a revised proposal that accepted the construction unit prices it had filed in January 2024 and lowered the overall construction cost while absorbing losses. It called for renewed negotiations, saying KHNP presented a revised contract proposal on Oct. 7 and allowed only three weeks for review, then refused a request to extend talks until the end of the year. KHNP responded that the proposal was intended to ease the builder’s burden in order to resolve differences that had dragged on for a long time.
Even with a change of builder, the questions of construction cost and allocation of responsibility remain. KHNP says competitive bidding can secure a reasonable price and terms, while Daewoo Engineering & Construction argues that, given rising costs and tightened requirements, a new builder’s estimate is more likely to come in higher. With only a limited number of companies able to take part, there are also limits to how far competitive bidding can push prices down, it said.
There are also concerns about schedule disruption. KHNP says it can keep to the planned timeline even after selecting a new builder, while the outgoing builder said the replacement process could delay construction by more than a year. Shim Hyung-jin, a professor of nuclear engineering at Seoul National University, said that “compared with a situation where the builder is already fixed, there is now a greater chance of disruption to work efficiency and follow-up tasks.”
Winding down the relationship with the existing consortium also remains. Ending the construction contract talks and terminating the joint cooperation agreement are separate procedures, requiring discussions on settling costs for work already performed and handing over design deliverables. If the matter escalates into legal disputes such as lawsuits or injunctions, it could add to the burden of selecting a new builder and transferring the work. KHNP says it will proceed with the selection of a new builder in parallel even if legal disputes arise, and will manage any additional costs from the changeover within the existing project budget.
With the Czech client also voicing concern over the delay in the construction contract, meeting the schedule is directly tied to confidence in South Korea’s nuclear exports. There is concern that if Team Korea’s first European project falters, it could affect follow-on projects in the United States and Vietnam. Yoo Seung-hoon, a professor in the Department of Future Energy Convergence at Seoul National University of Science and Technology, said “the government should mediate so that KHNP and the builder make mutual concessions and share the burden,” adding that “if the problem goes unresolved and construction is delayed, there could even be liability for liquidated damages.”
Kim Jung-kwan, Minister of Trade, Industry and Energy, said in a post on X, formerly Twitter, on the 29th that he “respects KHNP’s judgment that the selection of a new builder is unavoidable.”