Hyun Shin-kyun (second from left), CEO of LG CNS, and Franky Oesman Widjaja (third from left), chairman of Sinar Mas Group, attend the completion ceremony for an AI data center in Jakarta, Indonesia, on Jan. 1 local time. Photo courtesy of LG CNS - Seoul Economic Daily Technology News from South KoreaHyun Shin-kyun (second from left), CEO of LG CNS, and Franky Oesman Widjaja (third from left), chairman of Sinar Mas Group, attend the completion ceremony for an AI data center in Jakarta, Indonesia, on Jan. 1 local time. Photo courtesy of LG CNS

LG CNS (064400.KS) has completed construction of an artificial intelligence data center overseas, the first such project by a South Korean company.

The company said on the 2nd that it had finished building a 30-megawatt AI data center in Jakarta, Indonesia. LG CNS said it marks the first time a Korean company has built an AI data center abroad for an overseas client. The company also secured a customer for the facility’s entire capacity before completion. The project was commissioned last year by KMG, a joint venture between Indonesia’s Sinar Mas Group and Korea Investment Real Asset Management.

LG CNS designed the Jakarta facility to reliably support high-performance computing based on next-generation graphics processing units. Given the high heat output of AI servers, the center uses a hybrid cooling structure that combines air cooling and liquid cooling. The first phase employs an air-cooling system that circulates air to lower internal temperatures. In later phases, the company plans to add liquid cooling to control GPU heat more efficiently, providing cooling infrastructure optimized for high-density AI server environments.

LG CNS also built a power system capable of handling high-density environments of more than 300 kilowatts per rack, roughly 60 times the power required for a typical data center rack. The power infrastructure is redundant, allowing the facility to run stably around the clock on backup power if the main supply is interrupted.

The project also illustrates the group’s “One LG” strategy of pooling data center capabilities across its affiliates. LG Electronics (066570.KS) supplied air-conditioning systems and LG Energy Solution (373220.KS) provided batteries for the Jakarta center.

LG CNS is currently designing the next phase. Once completed, total power capacity will expand to 400 megawatts. Building on the Jakarta project, the company plans to expand its AI data center business across the Asia-Pacific region, including Japan, Thailand and Vietnam.

“Completing the AI data center in Indonesia is a meaningful achievement that allowed LG CNS to bring the data center capabilities it has built up at home to overseas clients and to prove its competitiveness in the global market,” said Hyun Shin-kyun, chief executive of LG CNS.