South Korean memory giant SK Hynix’s funding blueprint for U.S. expansion has run into complications. According to Reuters, citing people familiar with the matter, Solidigm—the company’s U.S. subsidiary—plans to invest about $45 billion to build two NAND flash memory plants in Marcy, New York. But the group had intended to first expand output at its Dalian, China plant to boost revenue and help fund the U.S. buildout, and the export licenses for the required U.S.-made equipment are stuck at the U.S. Department of Commerce and have not been approved.
At the heart of the dispute is whether the additional equipment for the Dalian plant constitutes a capacity expansion or simply filling existing space. SK Hynix argues that the relevant cleanrooms were completed back in 2023, so installing equipment into existing space should not be considered an expansion. The U.S. side insists it will not approve exports of U.S.-made equipment for technology upgrades or capacity expansion. The two sides have yet to reach consensus, but the Commerce Department has also not formally rejected the application.
The people familiar said Solidigm executives have met with U.S. Department of Commerce officials nearly ten times since late August, repeatedly revising the license application along the way. At a meeting last week, however, Commerce Under Secretary Jeffrey Kessler maintained the existing position, refusing to allow additional U.S.-made equipment for expanding or upgrading capacity at the China plant. It is understood that in late August, Solidigm co-CEO Richard Chin and other executives met with Commerce Secretary Howard Lutnick and Kessler, and U.S. officials at the time expressed interest in the potential investment and a U.S. NAND plant, and were open to seeking a solution.
Beyond the license for new equipment, the two sides are separately negotiating a 2027 export license for equipment needed to maintain day-to-day operations at the Dalian plant. The two licenses are different in nature: the former involves new production equipment, while the latter concerns whether the existing plant can keep operating.
New York investment could reach $100 billion
Solidigm’s New York plant proposal is the most closely watched investment in this dispute. Under the plan, the two NAND plants would involve an initial investment of about $45 billion, with total long-term investment potentially expanding to about $100 billion. NAND is memory that retains data after power is cut, and is widely used in solid-state drives and data-center storage equipment, with demand continuing to rise as artificial intelligence drives data-center expansion.
The investment, however, has not been finalized. Solidigm said it is evaluating potential locations for NAND plants globally and has not decided on any specific plan. SK Hynix also said in a filing with the U.S. Securities and Exchange Commission on October 29 that Solidigm is reviewing various options to enhance competitiveness and expand capacity, and has not made a decision.
The financing arrangement has also shifted. SK Hynix announced on October 23 that, given capital-market conditions and its share-price trend, it has stopped evaluating a potential Solidigm IPO and pre-IPO fundraising, but its need to expand capacity remains unchanged, and it will continue to assess investment timing, scale and other funding methods.
Trump administration faces policy dilemma
The case highlights the Trump administration’s tug-of-war between two policy goals: preventing advanced technology from flowing to China while attracting foreign semiconductor companies to expand investment in the U.S. Allowing the Dalian equipment could help bring about the large New York investment, but it also involves capacity and technology development in China that the U.S. had been unwilling to open up.
Leland Miller, a member of the U.S.-China Economic and Security Review Commission established by Congress, said the overall arrangement would ultimately need a green light from the White House to move forward. The White House and the U.S. Department of Commerce did not immediately respond to requests for comment, and SK Hynix did not respond outside business hours.
At the local level, there is hope for progress in the negotiations. Anthony Picente, county executive of Oneida County, New York, where the plant would be located, said he hopes for an answer within the next few weeks, noting that a federal investment tax credit expires at the end of the year, making the time pressure hard to ignore.
Dalian plant background and regulatory history
The equipment restrictions on the Dalian plant stem from the U.S. tightening export controls on China’s semiconductor industry in recent years. SK Hynix agreed in 2020 to acquire Intel’s NAND business for $9 billion, taking over the Dalian plant and the solid-state drive business along with it. Shortly after the deal closed, the U.S. imposed sweeping equipment export controls on advanced semiconductor plants in China.
The U.S. initially granted exemptions to foreign-owned chip plants in China, but the Commerce Department later revoked the existing authorizations and switched to an annual export licensing system, under which suppliers provide specific equipment and technology subject to volume limits. The Commerce Department made clear at the time that it did not intend to approve licenses for technology upgrades or capacity expansion—a policy line that SK Hynix must now cross to advance its New York investment.
Impact on markets and the industry
For SK Hynix, the Dalian and New York plans are intertwined. If the Dalian plant cannot smoothly bring in U.S.-made equipment to raise output and advance to more advanced processes, the group’s financial arrangement of using China plant revenue to fund U.S. investment will face a gap, which in turn could affect the timeline and scale of the New York buildout.
For the memory industry, the case is also seen as a bellwether for how tight or loose U.S. controls on China will be. If the U.S. ultimately gives the green light, it could set a precedent for other foreign companies with chip plants in China; if restrictions stay tight, it would mean the regional shift in NAND supply will accelerate, and the urgency of building U.S. domestic capacity will rise further.
Negotiations are still ongoing, the U.S. has not formally rejected the application, and Solidigm stresses that the New York investment amount and plant plan cannot yet be considered final. Going forward, the focus will be on the outcome of the export review and whether the company formally announces the investment plan.