South Korea’s Hanwha Ocean is re-entering the FLNG market—floating facilities for producing, storing and offloading liquefied natural gas—setting up a rematch with Samsung Heavy Industries, which controls 64% of the global market for newbuilds. The question is what niche a latecomer can target in a high-value offshore plant segment where each unit carries a contract value of 3 trillion to 4 trillion won (approximately $2.2 billion to approximately $3.0 billion).
At its third-quarter earnings call on October 29, Samsung Heavy Industries was asked whether any of its FLNG projects overlap with those pursued by Hanwha Ocean. “There are no cases where we are in direct competition with Hanwha Ocean,” the company replied, adding that “the project owners also do not appear to view Hanwha as an equal competitor to Samsung.” Industry observers read the remark as a display of confidence in its leadership position and as a message aimed at checking Hanwha Ocean’s return to the market.
Samsung Heavy Industries has won seven of the 11 newbuild FLNG units ordered worldwide, giving it a 64% share. Of the remainder, one went to Daewoo Shipbuilding & Marine Engineering—Hanwha Ocean’s predecessor—and three to China’s Wison Shipyard. The figures exclude conversions of LNG carriers.
Hanwha Ocean’s starting point is a world first. The former Daewoo Shipbuilding signed a contract with Malaysia’s state energy company Petronas in 2012 and completed the world’s first FLNG newbuild in May 2016. But oil and gas prices plunged in the second half of 2014, prompting a string of offshore gas field developments to be canceled or shelved, and the company absorbed massive losses on the Petronas project from design changes and schedule delays. After posting an operating loss of 3 trillion won (approximately $2.2 billion) in the second quarter of 2015, it entered creditor-led restructuring, and follow-on orders effectively stopped.
After Hanwha Group acquired Daewoo Shipbuilding in 2023 and relaunched it as Hanwha Ocean, the company began pushing the FLNG business in earnest last year. In November 2024, it joined Hanwha Aerospace in acquiring Singapore-based offshore plant company Dyna-Mac to bolster production capacity. At its earnings call on October 27, the company said “order opportunities for FLNG are growing as oil majors strengthen their LNG portfolios,” and that it would target new LNG projects in Venezuela, Mozambique and Nigeria.
The most concrete volume is a project in British Columbia being pursued with Canada’s Canada Clean Power. The venture, which would develop a 12-million-ton-per-year FLNG facility, followed a memorandum of understanding in June with an agreement in September under which Hanwha Ocean participates as a strategic partner and investor and takes charge of construction, ownership and operation. A final investment decision (FID) is targeted for early 2028.
Progress has also been made on securing a design foundation. In September, Hanwha Ocean obtained approval in principle (AIP) for a standard FLNG design from the American Bureau of Shipping (ABS) and Norway’s DNV. The plan is to extend the standardization approach it built in floating production, storage and offloading (FPSO) units to FLNG, shortening the initial engineering phase and improving project predictability. “The significance is less the certification itself than that the company has secured a design foundation that allows it to commercialize FLNG again,” a shipbuilding industry official said.
Samsung Heavy Industries, too, shares the scars of past low-price orders. The FLNG unit for Shell’s Prelude gas field off Australia, ordered in 2011, saw costs snowball due to design delays and additional work, and in 2015 the company booked the increased costs on its offshore plant order backlog all at once, posting an operating loss in the 1.5 trillion won (approximately $1.1 billion) range. In 2016, a contract worth about $4.7 billion to build three FLNG units for Shell was also canceled when development of Australia’s Browse gas field was shelved.
Nevertheless, Samsung Heavy Industries has all but monopolized FLNG orders placed since then. Its competitiveness is attributed to standardizing design, specifications and production methods and using repeat construction to raise predictability of schedules and costs. Samsung Heavy Industries is simultaneously building three large FLNG units at its Geoje shipyard: Petronas’ ZLNG of Malaysia, ENI’s Coral Norte of Italy and Canada’s Cedar FLNG. It is said to be the first time three large FLNG units have been built simultaneously at a single yard. It also plans to begin work on the first Delfin FLNG unit of the United States, which it won in June by beating Wison Shipyard.
The two companies’ recent FLNG order and project status is summarized below.
CategorySamsung Heavy IndustriesHanwha OceanNewbuild FLNG orders7 units (64% global share)1 unit (during predecessor Daewoo Shipbuilding era)Currently under constructionThree large units simultaneously (Geoje)Canada Clean Power project in progressStandardization/certificationStandardized design, specifications, productionAIP for standard design from ABS, DNVKey baseGeoje shipyardProduction capacity bolstered via Dyna-Mac acquisition
Note: Based on newbuilds; LNG carrier conversions excluded. China’s Wison Shipyard won the remaining three units.
The market environment is favorable for both companies. As oil majors expand their LNG portfolios, orders for floating liquefaction facilities are reviving. The variable is that FLNG contracts are large—3 trillion to 4 trillion won (approximately $2.2 billion to approximately $3.0 billion) per unit—and losses pile up all at once when design changes and schedule delays occur, so a larger order backlog does not automatically translate into improved profitability. The cost risks seen in the past Prelude and Petronas projects are a prime example.
For Hanwha Ocean, the company appears to be aiming beyond simple contracting to a role as project developer, leveraging its world-first construction record, standard design certification and equity participation in the Canadian project. Samsung Heavy Industries, by contrast, is defending against the latecomer’s entry by maintaining relationships with project owners based on its overwhelming market share and repeat-construction experience. The final investment decision for the Canada Clean Power project, expected in early 2028, and the timing of orders for new projects in Venezuela, Mozambique and Nigeria are expected to be decisive moments for the future shape of market share.