Samsung Electro-Mechanics has surpassed 1 trillion won in advance payments secured from global Big Tech customers under long-term supply contracts. As expanding AI infrastructure investment deepens shortages of multilayer ceramic capacitors (MLCCs) and semiconductor package substrates, customers are paying ahead of delivery to lock in supply.

According to the electronics industry on the 18th, Samsung Electro-Mechanics received $777 million (approximately 1 trillion won) in advance payments related to long-term product supply contracts with major customers as of the end of the third quarter. That is up 43.9% from $540 million (approximately 720 billion won) at the end of June, a gain achieved in just three months. The company’s supply contracts signed this year for key components—including silicon capacitors, AI server MLCCs, inductors and FC-BGA (flip-chip ball grid array) substrates—total about 5.18 trillion won (approximately $3.9 billion) on a disclosed basis.

The shortage is also visible in the numbers. According to market research firm TrendForce, MLCC lead times—the period from order to delivery—stretched to 40 weeks in mid-this month. That is eight weeks longer than the 32 weeks seen at the end of September and more than triple the 12 weeks considered normal. TrendForce has upgraded its assessment of MLCC supply-demand conditions to “Very Tight.” MLCC production lines have been running at essentially full capacity since the third quarter of this year, and inventories are at an all-time low.

AI server MLCCs carry more than 10 times the content of those in general servers. A single server rack is known to hold as many as 600,000 of them. Because they must withstand 24-hour operation in high-temperature, high-voltage environments, they must simultaneously deliver high capacitance and high reliability—which limits actual supply to a handful of manufacturers. Samsung Electro-Mechanics and Japan’s Murata supply most of the high-performance MLCC market for AI.

Prices are also climbing steeply. Samsung Electro-Mechanics’ cumulative average selling price (ASP) for MLCCs in the third quarter of this year rose 21.4% from last year’s annual average. The ASP for semiconductor package substrates rose 28.1% over the same period. The company is raising supply prices in consideration of competitors’ pricing policies and market supply-demand conditions.

ItemCumulative Q3 2026 ASP vs. Full-Year 2025MLCC+21.4%Semiconductor package substrate+28.1%

The price increases have translated into improved earnings. Third-quarter revenue at the Package Solutions division, which handles semiconductor package substrates, was 939 billion won (approximately $703.3 million), up 58% from a year earlier. Sales of high-value-added FC-BGA substrates used in AI accelerators and server central processing units (CPUs) drove the growth.

Samsung Electro-Mechanics plans to invest 10 trillion won (approximately $7.5 billion) over the next three years to expand FC-BGA production capacity. It has secured customers for most of the added capacity and will cover a significant portion of the investment with customer advance payments. The structure is to secure demand and funding for capital investment first through long-term supply contracts, then expand production facilities. The company is also developing next-generation products in parallel. It recently developed high-reliability MLCCs for the 48V output stage of AI server power supply units (PSUs) and large-area FC-BGA substrates for AI.

A Samsung Electro-Mechanics official said at the third-quarter earnings presentation: “Major Big Tech customers have recognized our technological capabilities and stable supply capacity, and we have completed large-scale investment support and long-term supply agreements. We will begin mass production in stages starting next year, with a full contribution to revenue from 2028.”

Securities analysts see the current shortage as a structural phenomenon rather than a short-term demand fluctuation. Yang Seung-soo, an analyst at Meritz Securities, said in a recent report: “Samsung Electro-Mechanics is maintaining 52-week long lead times and a rising price trend across all major MLCC categories—low-capacitance, high-capacitance and automotive. The continued lengthening of lead times suggests that a structural supply shortage in the MLCC market is persisting beyond short-term demand swings.”

Supply shortages are continuing not only for MLCCs but also for high-performance system semiconductors such as central processing units (CPUs) and graphics processing units (GPUs), as well as memory chips including DRAM and NAND. Lead times for Ajinomoto Build-up Film (ABF), a key material for semiconductor package substrates, have stretched to four times normal levels.

The situation shows that bottlenecks across the AI infrastructure supply chain are changing not only component unit prices but also contract structures. The practice of customers paying in advance is a means for component makers to secure both investment funding and demand at the same time, but it also signals that bargaining power within the supply chain has shifted toward component suppliers. If AI servers continue to become more advanced, tight supply and demand for high-performance MLCCs and high-value-added FC-BGA substrates is expected to persist for the time being.