South Korea’s Hanwha Ocean (042660) has effectively positioned itself to secure a floating liquefied natural gas (FLNG) project in Canada with total project costs of $15.7 billion (approximately ₩20.9 trillion). The move comes four months after the company ceded preferred bidder status to Germany in the approximately ₩55 trillion ($41.3 billion) Canadian Patrol Submarine Project (CPSP), and represents a larger order win on the offshore plant side—the very industrial cooperation card Hanwha Ocean played during that competition.

According to industry sources on the 18th, Hanwha Ocean signed a heads of agreement (HOA) with Canadian energy developer Canata Clean Power for the follow-on development of an LNG export facility project near Prince Rupert, British Columbia. The plan calls for deploying an FLNG unit producing up to 12 million tons of LNG per year, with a target for first shipment in 2032.

FLNG is a facility that liquefies and stores natural gas at sea before transferring it onto LNG carriers. Canata has laid out a blueprint to liquefy natural gas extracted from western Canada off the coast of Prince Rupert and export it to Asian markets. The 12 million tons represents the project’s maximum total production capacity.

The pace at which the two companies have moved through agreement stages has been rapid. After signing a memorandum of understanding (MOU) in June, they signed provisional cooperation terms in September, and have now reached their third agreement, the HOA. In September, Hanwha Ocean also received approval in principle for its proprietary standard FLNG design from the American Bureau of Shipping (ABS) and Norway’s DNV, giving its technology external validation.

Still, hurdles remain before the project can be completed. Final site selection, gas supply and transportation contracts, environmental permitting, and financing all remain unresolved. The fact that the 2032 shipment target was set before key terms were finalized is read as a sign of both parties’ strong commitment to pushing the project forward.

This project is the card Hanwha Ocean put forward as a local industrial cooperation measure when it entered Canada’s submarine competition. The Canadian government has made benefits to domestic industry and technology a key evaluation criterion in major defense procurement reviews, and Hanwha Ocean argued it could contribute as a key East Asian nation to a project exporting western Canadian natural gas to Asia. However, in July the Canadian government selected Germany’s ThyssenKrupp Marine Systems (TKMS) as the preferred bidder and Hanwha Ocean as the backup supplier.

Even after the submarine door closed, consultations with Canata did not stop. Some assessments suggest that trust built during the bidding process instead carried over into a private-sector energy project. A Hanwha Ocean official said, “The signing of this heads of agreement is meaningful in that the two companies have moved one step beyond their existing comprehensive cooperative relationship into a stage of specifically reviewing the technical feasibility and commercial competitiveness of the Canadian LNG project,” adding, “Based on the offshore plant design and construction capabilities we have accumulated, we plan to participate in project development and contribute to raising the project’s feasibility.”

Hanwha Ocean is exploring participation across the entire project—from design to construction and operation. The company’s FLNG design standards and offshore plant construction experience are expected to be key leverage at the negotiating table.

ItemDetailsProjectCanata LNG (near Prince Rupert, British Columbia)Facility typeFloating liquefied natural gas production unit (FLNG)Maximum capacity12 million tons per yearTotal project cost$15.7 billion (approximately ₩20.9 trillion)Target for first LNG shipment2032Agreement historyJune 2026 MOU → September provisional cooperation terms → November HOARemaining proceduresFinal site selection, gas supply and transportation contracts, environmental permitting, financing

Note: The won conversion of total project costs is approximately ₩20.9 trillion based on $15.7 billion.

Market observers suggest this project could mark a turning point for the shipbuilding cycle. With global LNG demand growing centered on Asia, if FLNG orders—which have shorter construction periods and fewer siting constraints than onshore terminals—revive, Hanwha Ocean’s offshore plant division could gain a foothold for an earnings rebound after several years. The $15.7 billion figure previously presented by Canata includes not only facility orders but also ancillary infrastructure, meaning the actual contract value is expected to vary depending on final design and contract structure.

Concerns about an order gap from the submarine loss also appear likely to ease. If the scenario of filling the disappointment in the defense sector with private-sector energy infrastructure materializes, the order portfolio—previously heavily dependent on specific projects—will become more diversified. However, with environmental permitting and financing remaining long-term challenges, some cautious voices also note that it is too early to treat the HOA as a final order win.