{"id":186286,"date":"2026-10-13T03:02:09","date_gmt":"2026-10-13T03:02:09","guid":{"rendered":"https:\/\/www.europesays.com\/korea\/186286\/"},"modified":"2026-10-13T03:02:09","modified_gmt":"2026-10-13T03:02:09","slug":"seoul-races-to-meet-30000-housing-starts-as-year-end-filings-cluster","status":"publish","type":"post","link":"https:\/\/www.europesays.com\/korea\/186286\/","title":{"rendered":"Seoul races to meet 30,000 housing starts as year-end filings cluster"},"content":{"rendered":"<p><img src=\"https:\/\/www.europesays.com\/korea\/wp-content\/uploads\/2026\/10\/JA7CE6VAYNJOFFTQBIVSVHDQEQ.jpg\" alt=\"Seoul Mayor Oh Se-hoon delivers remarks at the joint cooperation agreement ceremony and special progress meeting for 11 redevelopment projects scheduled to break ground in the second half of 2026 at Seoul City Hall on the 13th. \/Courtesy of Yonhap News\" height=\"410\" width=\"616\" decoding=\"async\"  loading=\"lazy\"\/>Seoul Mayor Oh Se-hoon delivers remarks at the joint cooperation agreement ceremony and special progress meeting for 11 redevelopment projects scheduled to break ground in the second half of 2026 at Seoul City Hall on the 13th. \/Courtesy of Yonhap News<\/p>\n<p class=\" article-body__content article-body__content-text | text--black text font--size-sm-18 font--size-md-18 font--primary\">Whether Seoul City meets this year&#8217;s goal to break ground on 30,000 dwellings in maintenance projects hinges on the remaining 11 business sites. The volume that has completed groundbreaking filings is about 15,000 dwellings, or half the goal. With roughly 80 days left until year-end, the city must push to start construction on the remaining 16,117 dwellings. Because some business sites are clustered in December, construction cost talks and permitting procedures are variables. Seoul Mayor Oh Se-hoon said, &#8220;We will definitely complete the groundbreaking target by this Christmas.&#8221;<\/p>\n<p class=\" article-body__content article-body__content-text | text--black text font--size-sm-18 font--size-md-18 font--primary\">According to Seoul City on the 13th, the city held a &#8220;joint cooperation agreement ceremony for achieving the housing supply goal&#8221; at City Hall that day, chaired by Mayor Oh. Eleven maintenance project associations pushing for groundbreaking within the year, five Sigongsa, and eight district offices took part and agreed to resolve delay factors by establishment and divide up the roles needed to break ground.<\/p>\n<p class=\" article-body__content article-body__content-text | text--black text font--size-sm-18 font--size-md-18 font--primary\">Seoul City has been intensively managing a total of 25 maintenance business sites with the goal of breaking ground this year. Of these, 14 sites, or about 15,000 dwellings, have completed groundbreaking filings. The city counts groundbreaking performance based on filing. If 16,117 dwellings at the remaining 11 sites complete filings within the year, the city can surpass the 30,000-dwelling goal.<\/p>\n<p class=\" article-body__content article-body__content-text | text--black text font--size-sm-18 font--size-md-18 font--primary\">Among the remaining business sites, Hannam District 3 in Yongsan District is the largest with 5,970 dwellings. Bangbae District 13 in Seocho District with 2,228 dwellings, Sinwolgol District 1 in Seongbuk District with 2,200 dwellings, and Macheon District 4 in Songpa District with 1,254 dwellings are also slated to break ground within the year. Noryangjin Districts 4, 5, and 7 in Dongjak District are also included.<\/p>\n<p class=\" article-body__content article-body__content-text | text--black text font--size-sm-18 font--size-md-18 font--primary\">The scheduled groundbreaking volume at Hannam District 3 and Bangbae District 13 is 8,198 dwellings, accounting for 50.9% of what remains. Adding Sinwolgol District 1 and Macheon District 4 brings the total to 11,652 dwellings, or 72.3%. The timeline at a handful of large business sites will determine whether the annual groundbreaking target is met.<\/p>\n<p class=\" article-body__content article-body__content-text | text--black text font--size-sm-18 font--size-md-18 font--primary\">On the 15th of last month, the integrated review plan covering eight areas\u2014including architecture, landscape, traffic, and education\u2014at Hannam District 3 was conditionally reported and approved by the Seoul City Maintenance Project Integrated Deliberation Committee. The dismantling work progress rate that Seoul City released last month was 99%, meaning demolition is in its final stage. The city plans to finish dismantling within the year and push to start the main construction. It will also start this year on infrastructure works such as roads within the district and proceed in parallel with procedures to approve changes to the project implementation plan that reflect the integrated review results.<\/p>\n<p><img src=\"https:\/\/www.europesays.com\/korea\/wp-content\/uploads\/2026\/10\/KZUA4VZY6ZFYXFMQ4445XBEPMU.jpg\" alt=\"Oh Se-hoon, mayor of Seoul, greets representatives from redevelopment associations and construction firms while attending the joint cooperation agreement ceremony for achieving dwellings supply targets at Seoul City Hall on the morning of the 13th. \/Courtesy of Lee Kyung-tak\" height=\"462\" width=\"616\" decoding=\"async\"  loading=\"lazy\"\/>Oh Se-hoon, mayor of Seoul, greets representatives from redevelopment associations and construction firms while attending the joint cooperation agreement ceremony for achieving dwellings supply targets at Seoul City Hall on the morning of the 13th. \/Courtesy of Lee Kyung-tak<\/p>\n<p class=\" article-body__content article-body__content-text | text--black text font--size-sm-18 font--size-md-18 font--primary\">Other business sites must also complete remaining steps\u2014such as construction cost adjustments, dismantling work, and permitting\u2014before they can break ground. If negotiations over construction costs between the association and the Sigongsa drag on or administrative procedures are delayed, the schedule to break ground within the year could be affected.<\/p>\n<p class=\" article-body__content article-body__content-text | text--black text font--size-sm-18 font--size-md-18 font--primary\">At a meeting that day, Kim Seong-bo, Seoul City&#8217;s second vice mayor for administration, said, &#8220;The last volumes are piled up in December,&#8221; and added, &#8220;We will convene again at year-end to review each business site&#8217;s progress and whether agreed items are being implemented.&#8221; Kim went on, &#8220;We ask that the association and the Sigongsa resolve construction cost disputes amicably, and that district offices swiftly handle administrative procedures such as permitting.&#8221;<\/p>\n<p class=\" article-body__content article-body__content-text | text--black text font--size-sm-18 font--size-md-18 font--primary\">Through this agreement, Seoul City asked associations for transparent operations and swift decision-making, and asked Sigongsa to disclose construction cost information and reasonably reduce costs. Seoul City and district offices will promptly process permitting procedures and step in to mediate if construction cost disputes arise. While moving up groundbreaking schedules, the city said it will maintain on-site safety and quality control.<\/p>\n<p class=\" article-body__content article-body__content-text | text--black text font--size-sm-18 font--size-md-18 font--primary\">Mayor Oh said, &#8220;We will directly identify the causes that slow progress at each business site and make necessary decisions swiftly without delay,&#8221; and added, &#8220;Seoul City and district offices will help facilitate talks between the association and the Sigongsa over construction costs.&#8221;<\/p>\n<p class=\" article-body__content article-body__content-text | text--black text font--size-sm-18 font--size-md-18 font--primary\">Since releasing its plan to accelerate housing supply in July last year, Seoul City has held 22 working-level progress acceleration meetings to check delay factors by establishment. Since July this year, the city has strengthened its management system through special progress meetings chaired by the second vice mayor for administration. In August, it checked the progress at business sites slated to break ground in the second half at the Hannam District 3 site.<\/p>\n<p class=\" article-body__content article-body__content-text | text--black text font--size-sm-18 font--size-md-18 font--primary\">At the special progress meeting held after the agreement ceremony that day, participants discussed remaining procedures at 11 business sites, including construction cost adjustments, dismantling work, and permitting. Seoul City will directly address conflicts that are difficult to resolve at the district level and, by checking each business site&#8217;s work schedule, prepare follow-up measures if delays are deemed likely.<\/p>\n<p class=\" article-body__content article-body__content-text | text--black text font--size-sm-18 font--size-md-18 font--primary\">Starting with 30,000 dwellings this year, Seoul City set a goal to break ground on a total of 310,000 dwellings in maintenance projects by 2031. To that end, it is also intensively managing 85 key supply strategy projects slated to break ground by 2028, totaling about 85,000 dwellings. Of these, about 69,000 dwellings will proceed on the existing timeline, while about 16,000 dwellings with potential delays will be managed separately.<\/p>\n<p>\u203b This article has been translated by AI. Share your feedback <a class=\"font--tertiary font--size-md-16 font--size-sm-16 text--grey-60 text--underline\" style=\"border-bottom:0\" href=\"javascript:throw new Error('React has blocked a javascript: URL as a security precaution.')\">here.<\/a><\/p>\n","protected":false},"excerpt":{"rendered":"Seoul Mayor Oh Se-hoon delivers remarks at the joint cooperation agreement ceremony and special progress meeting for 11&hellip;\n","protected":false},"author":2,"featured_media":186287,"comment_status":"","ping_status":"","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[3],"tags":[61703,1149,22264,112,57912,14469],"class_list":["post-186286","post","type-post","status-publish","format-standard","has-post-thumbnail","category-seoul","tag-maintenance-project","tag-oh-se-hoon","tag-redevelopment","tag-seoul","tag-seoul-city","tag-seoul-mayor"],"_links":{"self":[{"href":"https:\/\/www.europesays.com\/korea\/wp-json\/wp\/v2\/posts\/186286","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.europesays.com\/korea\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.europesays.com\/korea\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.europesays.com\/korea\/wp-json\/wp\/v2\/users\/2"}],"replies":[{"embeddable":true,"href":"https:\/\/www.europesays.com\/korea\/wp-json\/wp\/v2\/comments?post=186286"}],"version-history":[{"count":0,"href":"https:\/\/www.europesays.com\/korea\/wp-json\/wp\/v2\/posts\/186286\/revisions"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.europesays.com\/korea\/wp-json\/wp\/v2\/media\/186287"}],"wp:attachment":[{"href":"https:\/\/www.europesays.com\/korea\/wp-json\/wp\/v2\/media?parent=186286"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.europesays.com\/korea\/wp-json\/wp\/v2\/categories?post=186286"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.europesays.com\/korea\/wp-json\/wp\/v2\/tags?post=186286"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}