Extremadura faces one of the greatest opportunities for industrial transformation in its recent history. On the table there are more than 7,350 million euros of private investment linked to four large data center projects that could generate around 2. …620 jobs, including those associated with construction and those in the facilities’ activity. A business bet of enormous dimensions that, however, faces the uncertainty generated by the royal decree that the Government approved this Friday. The Board fears that new energy and environmental demands will end up stopping investments that it considers strategic for the future of the community.
The Executive establishes a common framework to order the implementation of data centers, facilities whose electrical consumption can reach large dimensions and that have become fundamental pieces for the development of artificial intelligence, cloud services and the digital economy. The standard conditions access to the electrical grid to compliance with a series of sustainability, energy and water efficiency requirements, in addition to incorporating obligations related to sovereignty and digital resilience.
The point that most concerns the regional administrations and part of the sector is the requirement that at least 80% of the annual electricity consumption of these facilities be supported by renewable energy. The text establishes that this coverage be accredited through self-consumption, storage or long-term supply contracts, of more than six years, with renewable facilities that have come into operation a maximum of 36 months before the data center, with some exceptions. It also introduces additionality conditions, with the aim that the demand for these facilities is accompanied by new renewable generation, and a time correlation criterion so that clean electricity coincides with the hours of consumption.
The decree incorporates some flexibility with respect to the initial proposal. It expands the age margin of renewable installations that can be linked to the centers, contemplates storage using batteries and establishes adaptation periods for certain obligations. However, it maintains the core of the demands, especially the objective of renewable coverage. Failure to comply with the requirements can lead to penalties and, ultimately, put the rights of access and connection to the electrical grid at risk.
The approval of the royal decree now opens a period of adaptation for projects that are already in process. In general, they will have six months to adapt to the new requirements, while the period will be three months for those who are pending a contest for access to the electricity grid. The text also contemplates financial compensation for non-compliance and sanctions that, in the most serious cases, can suspend access and connection rights for three years.
Extremaduran rejection
The Extremadura Government has expressed very clearly its rejection of the regulation. He considers that the decree is “disproportionate” and may harm fundamental investments for the industrial development of the region. The Minister of Industry, Mercedes Morán, already warned that the text was “contrary to the interests of Extremadura and Spain” and defended that data centers should be considered “a strategic infrastructure.” Their argument is that the community has a privileged position due to its renewable generation capacity and availability of land, and that this advantage must be translated into economic activity: “We cannot be producing clean energy so that added value and employment are generated in other territories.”
The position of the regional government is to demand regulation that takes into account the particularities of each territory and that allows guaranteeing the sustainability and security of the system without blocking industrial projects. The concern is not limited to the possibility that new initiatives decide not to establish themselves in Extremadura. It also covers projects that are already in administrative and business progress and that must check whether they can adapt to the conditions that the Executive has finally established.
Extremadura demands from the Government a regulation that takes into account the particularities of each territory: “We cannot produce energy (…) so that employment is generated in other territories”
According to the figures provided by the Ministry of Economy, the largest investment planned corresponds to Lusitanus, the project promoted by FRV in ExpacioMérida, which plans to allocate 2.8 billion euros to its first phase. The company has formalized a purchase option for the land, covering an area of 240,000 square meters, and has requested an electricity consumption point at the Don Álvaro substation, still pending resolution by Red Eléctrica. According to the data provided by the company, more than 80% of its planned consumption will be supplied by renewable self-generation. In terms of employment, it estimates between 1,700 and 2,000 jobs during construction and more than 120 direct jobs during operation.
In Badajoz, Data Riocaya projects an investment of 1,913 million euros and 330 jobs. The center will be located on the Southwestern European Logistics Platform and will be oriented towards data computing and artificial intelligence, with a grid access capacity of up to 300 megawatts. The initiative has made progress in the availability of land: the company has already formalized the sale and purchase of four plots totaling more than 198,000 square meters, where it plans to develop the center and its supply infrastructure. The project has been declared a Business Project of Autonomous Interest (PREMIA), although it still has pending energy procedures. Among them is the authorization of the 400 kilovolt line, a state responsibility, while the 220 kilovolt line has favorable authorization.
Merlin Edged contemplates an investment of more than 1.6 billion euros for its data center in Navalmoral de la Mata. The project foresees two units on a plot of more than 206,000 square meters in the North Industrial Park of Extremadura and around 250 jobs. The initiative is close to the environmental resolution of its first phase, according to the information provided by the Board, and the company, directed by Ismael Clemente from Extremadura, has already requested permission for the earthworks.
The fourth project is CC Green, in Cáceres, which foresees a private investment of 1,040 million euros and 220 jobs during the first year of activity. Its objective is to build a carbon-neutral, state-of-the-art data processing center, aimed at the digital economy and technological services. It has the PREMIA declaration, although its development is in an initial phase and is conditional on the unlocking of the industrial estate where it intends to settle.
Together, the four projects represent more than 7,353 million euros of planned private investment and around 2,620 jobs, according to the calculation provided by the Board. Three of them have the declaration of Business Project of Autonomous Interest.