A Westinghouse-Bechtel consortium and Poland’s state nuclear developer said Sept. 23 they have agreed on the main commercial terms of an EPC contract for the country’s first nuclear power plant.

The agreement with Polskie Elektrownie Jądrowe moves the three-unit project, featuring the Westinghouse AP1000 reactor design, closer to a final construction contract after engineering and site work advanced for months while negotiations continued. The parties aim to complete negotiations by year-end.

A day later, Bechtel awarded a Polish consortium led by Polimex Mostostal a design-build contract valued at about $80 million for two module assembly buildings where some of the largest reactor components will be assembled near the construction site.

]]>

Polskie Elektrownie Jądrowe and the Westinghouse-Bechtel consortium “have agreed on the main terms of the contract for the construction of the first Polish nuclear power plant,” the Polish state-owned entity’s President Marek Woszczyk said in a statement. The agreement, he said, provides the basis for “further, detailed negotiations” over the remaining EPC terms. 

Neither an EPC contract value nor the commercial terms agreed to so far were disclosed.

ENR reported in August that the consortium and Polskie Elektrownie Jądrowe were performing work originally expected under the EPC contract through an extended engineering development agreement, including nuclear-island, turbine-island and balance-of-plant design.

Three Westinghouse AP1000 units will provide 3,750 MWe of generating capacity at the Lubiatowo-Kopalino site in Choczewo near Poland’s Baltic Sea coast. Polskie Elektrownie Jądrowe transferred management of the 740-acre site to Bechtel in August, when large-scale grading, drainage and temporary-road construction were getting underway.

]]>

Looking for quick answers on construction and engineering topics?
Try Ask ENR, our new smart AI search tool.

Ask ENR →

At an estimated $52 billion, according to the European Commission, the project is being financed through a mix of state capitalization and external debt. Poland has authorized about $15.8 billion in state capitalization for Polskie Elektrownie Jądrowe, with the financing structure calling for 70% of project costs to come from external debt.

Module Assembly Contract Awarded 

Polimex’s contract covers engineering and design documentation needed to obtain permits as well as materials, structural erection, testing, acceptance and final turnover of both buildings. The contract has a 1,158-day performance period, with compensation combining lump-sum and cost-estimate components and subject to indexation under specified conditions.

]]>

CA01 structural module lifted into the Vogtle Unit 3 nuclear island.

A 1,140-ton CA01 structural module is lifted into the Vogtle Unit 3 nuclear island in Georgia in 2015. Poland’s similar AP1000 project will use two new assembly buildings to also construct massive reactor modules onsite.

Photo courtesy Georgia Power

Each building will measure about 423 ft long, 180 ft wide and 144 ft high, with reinforced-concrete piles and columns supporting a reinforced-concrete slab and structural-steel frame enclosed by insulated panels and a roof system.

Climate controls will allow welding and assembly to continue around the clock while protecting work from precipitation, wind and extreme temperatures. Each building will contain three overhead bridge cranes—two rated at about 138 tons and one at about 66 tons—to maneuver components.

These will be Poland’s first facilities used to assemble nuclear-island components weighing more than 1,000 tons, Bechtel Polska President Leszek Hołda said in a statement. The contract is the first to directly support construction of the plant’s nuclear area, he said.

AP1000 nuclear construction relies heavily on prefabricated structural and mechanical modules. The largest, including the roughly 1,000-ton CA01 structural module, will be assembled in the temporary buildings because components weighing hundreds of tons cannot be transported to the site fully assembled.

Crews will also assemble containment-vessel rings and the containment roof, along with shield-building panels. Work inside the structures will include nondestructive weld examinations, pressure testing and precision surveying and certification before completed modules are lifted by a ring crane and placed on the generating-unit foundation.

Polish Contractors Take Larger Role 

More than 10 major contracts with Polish subcontractors have been placed this year, along with smaller awards, according to Poland’s Energy Ministry. It estimates the combined value of contracts awarded to Polish firms on the Lubiatowo-Kopalino project at more than $570 million.

]]>

Construction of the new national road serving Poland’s first nuclear power plant.

Polish contractors are building the new national road serving the Lubiatowo-Kopalino nuclear plant, including earthwork, drainage and ground improvement. Polimex companies are part of the design-build team for the roughly seven-mile first road section.

Photo courtesy GDDKiA

Budimex is performing earthwork and temporary infrastructure construction, DORACO is supporting geological and geotechnical investigations and Unihouse is building support facilities for 1,000 workers. Other Polish contractors are developing the project’s materials laboratory and providing site security. A consortium that includes Polimex Mostostal affiliates is also building the roughly seven-mile first section of a new national road serving the nuclear plant under a design-build contract valued at more than $46 million.

The EPC agreement does not itself authorize nuclear construction. Polskie Elektrownie Jądrowe submitted its nuclear construction-license application in March and plans to apply for a separate building permit in 2027. Current field activity remains preparatory work, with first nuclear concrete targeted for the fourth quarter of 2028.

Commercial operation of the three units remains targeted for 2036, 2037 and 2038, respectively. Woszczyk said in a statement that the consortium will be responsible for building the plant, with first electricity expected to reach Poland’s grid in 2036.