Hobbs said the preliminary work was complete, but the project was on hold while ministers considered how a direct award could be made. He believed such an award was not currently lawful. It might become possible next year after planned changes to CMAL’s governance, and the board would have to be instructed by ministers as sole shareholder. “While we want to see that shipyard survive, we do not believe building ferries there is the right thing to do for the island communities,” he said, pointing to the delays and overspends on GLEN SANNOX and GLEN ROSA. In a letter to Transport Scotland he described a direct award as “problematic at best and folly at worst”, and said CMAL wanted an open international tender.

Transport Secretary Stephen Flynn told the same session that the government remained committed to the direct award. Ferguson Marine said it had a proud shipbuilding record. The GMB union said CMAL was itself responsible for many of the problems. CMAL has not placed a shipbuilding contract with a UK yard since 2015. The first phase of the programme, seven small ferries, went to Remontowa in Gdansk last year.

At the same hearing, MSPs were told that GLEN SANNOX and GLEN ROSA may never run on the LNG they were designed for, The Scotsman reports. The cost of the fuel and of building storage tanks at the ports puts its use in doubt. “There is a question mark. It will hinge on the investment case to put LNG facilities to where that vessel will run from,” CalMac chief executive Duncan Mackison said. He agreed that CalMac would not use LNG if the price was too high. Hobbs said LNG had been seen as the “fuel for the future” but its price had “escalated beyond anything anybody could ever have imagined”. Committee convener Willie Rennie called the situation the “ultimate farce”.

GLEN SANNOX entered service last year, six years late. Because Scotland has no LNG supply, the fuel had to be brought 500 miles by road tanker from Kent. She was first deployed on Troon–Brodick, then moved in the summer to the Western Isles, where there is no access to LNG. GLEN ROSA is due on the Arran route next spring if she is completed by her latest deadline in February. Both ships are four times over budget.

© Shippax