Google will build its first Wyoming data center, a $17 billion campus in Cheyenne, and the announcement arrived with much of the power supply already under contract. American Electric Power (AEP) will serve the site from a 702-megawatt (MW) fuel cell plant running on natural gas, and gas generators operated by Tallgrass Energy and Black Hills Energy will add supply, according to Google’s announcement.
Google calls the fuel cell development the largest of its kind planned and says carbon capture and storage will keep a large majority of the plant’s emissions out of the atmosphere. The company’s announcement gives no capture rate and no figure for the campus’s total electricity load. Project details in this piece come from announcements by Google, AEP and Intersect, a Google subsidiary.
AEP Owns the Cheyenne Plant and Sells to Google for 20 Years
AEP set out the financing in its Oct. 14 release. The utility plans to spend about $4 billion on the project, which will sell its output to Google under a 20-year power purchase agreement. The plant will be held by Cheyenne Fuel Cell LLC, owned about 92% by AEP, with funds advised by Basalt Infrastructure Partners holding the rest. Construction is due to begin in 2026, and AEP expects full operation by the end of 2028.
The Bloom Energy units generate electricity through an electrochemical reaction, without burning the gas. Bloom has taken the same technology to other AI developers, including a $5 billion alliance with Brookfield to build data centers on onsite fuel cells. Carbon dioxide captured at Cheyenne is slated for Tallgrass’s Eastern Wyoming Sequestration Hub. Google also plans a front-end engineering and design study on fitting capture equipment to Tallgrass’s combined-cycle turbines, an evaluation that stops short of a commitment to install it.
Google says it will pay for 100% of the power the campus uses and cover infrastructure needs driven directly by its growth. The buildings will be air-cooled to limit demand on local water. The company expects the project to generate hundreds of millions of dollars in property taxes for Laramie County and Laramie County School District 1, and it is forming a community council with its energy partners to take up local concerns about data center growth.
In Texas, Google Owns the Generation Developer
The arrangement looks different in the Texas Panhandle. In June, Google and Intersect announced the Meitner Energy Center in Gray and Roberts counties, a data center built alongside more than 1 gigawatt of wind, solar and battery storage. Google closed its purchase of Intersect in March, so the load and the generation sit under one parent.
Intersect says clean energy will cover most of the site’s power from the first day, with on-site gas firming a smaller share. Google expects the setup to reduce the need for new supply from the local grid. Developers have been weighing electrical capacity ahead of land when choosing data center sites, which has pushed more of them toward onsite generation.
Michigan Attorney General Seeks Rehearing on DTE Contract
In Michigan, the cost protections are written into a utility contract. On Oct. 1, the Michigan Public Service Commission (MPSC) approved special contracts between DTE Electric and Google for a data center in Van Buren Township, Wayne County, in Case No. U-22058. The supply agreement runs 20 years, against the five-year term normally required under DTE’s large-load rate. Google must pay for at least 80% of its contracted demand, compared with 50% to 65% under the general rate, and would owe at least 15 years of minimum monthly charges if it cancels early. Payment floors and collateral terms of this kind now show up in large-load tariffs in a growing number of states.
A second agreement has Google paying for up to 1,600 MW of renewable generation and 480 MW of battery storage, which DTE will develop, own and operate. The contracts also require credit and collateral in case the data center shuts down early. DTE projects the deal will cut costs for its other customers by $1.7 billion over the 20-year term.
Attorney General Dana Nessel is contesting that projection. Her office filed a petition for rehearing on Oct. 30 arguing that the commission let DTE net costs against benefits across the full contract term, a method the petition says leaves other customers subsidizing the data center from 2035 through 2038. The filing also objects to a cap on collateral owed by Google and parent Alphabet and says DTE has not accounted for transmission costs. Nessel wants costs and benefits reconciled every year, and she asked the commission to reject the contracts if it will not adopt her recommendations. She took a similar fight over DTE’s Saline Township data center contracts to the state Court of Appeals in April, after the commission approved them.
Construction Dates and a Pending Petition
AEP has said construction on the fuel cell plant will begin in 2026. In Michigan, Nessel’s petition is pending before the commission, and DTE expects to begin serving the Van Buren Township site in December 2027, reaching full load by December 2028.