Jon ChrisosPORTLAND, Maine —

The Portland City Council unanimously approved a plan Monday night to redesign Franklin Street, advancing the project to preliminary design with the Maine Department of Transportation.

Franklin Street is about 200 feet wide in some places. The plan would narrow the roadway and add raised crossings and separated bike lanes. It would reconnect streets and add sidewalks, traffic-calming features and on-street parking. The plan also keeps two through lanes in each direction on the northern stretch, from Marginal Way to Congress Street, and one lane each way on the southern stretch, from Congress to Commercial Street.

The conceptual plan aims to create more than 3.5 acres of land for housing and other development, expand Lincoln Park and make room to enlarge Boyd Street Park and Garden. The plan estimates that newly created parcels, combined with some adjacent city-owned land, could accommodate 530 to 720 homes.

The project grew from a 2024 city agreement with MaineDOT to update an earlier Franklin Street study. The Sustainability and Transportation Committee voted 3-0 in October to send the plan to the council.

Written comments submitted before the vote included support and objections. The Portland Bicycle and Pedestrian Advisory Committee supported the plan, citing safety and connectivity improvements, but urged further review of turn lanes and medians. The Urbanist Coalition of Portland also backed moving ahead while arguing some parking, medians and traffic lanes could be reduced to create more room for housing.

Other commenters raised concerns about tree loss, commuter traffic shifting to Pearl Street, parking for future residents and project costs.

The preliminary construction estimate is about $44.4 million, including $12.5 million for stormwater, sewer separation and green stormwater infrastructure. The estimate will be refined during design. The plan anticipates construction from 2031 to 2033.

The preliminary design phase is already funded at $2.5 million. After that, the project would need final design and construction funding.