Southern California Edison’s announcement Tuesday, Nov. 24, that it has extended the deadline to apply for its wildfire recovery compensation program one month was met with approval, but also questions about the company’s motives amid continued concerns about the time crunch facing survivors.
Speaking Monday, Nov. 23, Edison International President and CEO Pedro Pizarro said the extension will be the only one and that the program application window will close on Dec. 31.
After months of urging eligible residents to apply by the Nov. 30 deadline, SCE said the combination of public feedback and the high volumes of claim submissions in the last few months led to the decision to extend the deadline.
“We needed to make sure that it was feasible from a resources perspective and we were able to make that work through the end of the year,” Pizarro said. “So that will give people a total of 14 months from the inception of the program, from the launch, to consider putting a claim in.”
Pizarro reiterated that Dec. 31 is the deadline for submitting an application, not the deadline to receive or accept an offer from SCE. Those currently in ongoing litigation can still apply to the compensation program, but must do so through their legal representative.
Those who accept an SCE compensation program offer give up the right to sue SCE for damages related to the Eaton fire. But for many survivors, the new deadline coincides with the deadline to apply to sue for noneconomic damages, which is Jan. 7, 2027.
In August, the Los Angeles County Fire Department released a report that found SCE’s equipment sparked the catastrophic Eaton fire, which killed at least 19 people and destroyed thousands of homes.
The Los Angeles County District Attorney’s Office has ongoing investigation into the public utility for potential criminal liability.
Pizarro said he’s confident that there is no basis for criminal liability or any basis that SCE leadership acted with conscious or willful disregard for public safety.
At its most recent meeting, the Altadena Town Council formally requested SCE to extend the compensation program submission deadline to January and to return in December to assess whether a further extension would be needed.
In addition, the Town Council asked that any extension “would explicitly state that SCE cannot use this as a justification for an extension of the trial.”
Local leaders welcomed the action, but suggested it might not be long enough.
“Last week The Altadena Town Council had a passionate public conversation about extending the deadline for the SCE Compensation Fund and we are grateful for the response by SCE,” said Nic Arnzen, chair of the council, an advisory board to the L.A. County Board of Supervisors. “We hope they will continue to monitor the wellbeing and capacity of the community and if it seems a further extension is desired, I hope they will continue to listen.”
Altadena resident and Town Councilmember Morgan Whirledge said in an email Tuesday that while the extension was welcome news for the community, 13 months was not enough time for information about the program to reach community members still dealing with displacement and stress.
Whirledge said one additional month of time is not enough of an extension.
“If applications continue trending upward at the Dec. 31 deadline, I would urge SCE to extend the program through Q1 of next year—beyond the holiday rush and past the two-year mark when many residents’ additional living expenses (ALE) insurance coverage runs out,” Whirledge said. “Granting the full extension our Council requested gives our residents the best chance to access the support they need.”
After the date for the first trial — on the thousands of claims against SCE — was pushed back six weeks to March 2027, some on the Town Council expressed concern that pushing the compensation program application deadline would provide SCE lawyers a reason to request further trial delays.
“These are separate tracks,” Pizarro said of the trial and the compensation program. “There really isn’t that interaction.”
Pizarro said SCE’s legal team is considering whether the delay to March is sufficient to prepare for trial due to the volume of discovery in the case and that decision is “happening on its own track.”
In its press release announcing the deadline extension, SCE cited the delay in the first trial and that it can take years in some instances for plaintiffs in litigation to receive payouts.
But attorneys representing survivors have pushed back on the utility, saying the program is an effort to limit how many legal cases the company is facing and that those that accept an offer typically get 30 to 50 cents on the dollar of what they could get through a negotiated settlement.
Gerald Singleton, a plaintiff attorney in the lawsuits against SCE, said Tuesday that the announced extension is not a surprise.
“They are simultaneously doing everything possible to delay trials while encouraging their victims to accept pennies on the dollar in their ‘take it or leave it’ program,” Singleton said in an email. “Edison’s gross negligence killed 19 people and destroyed 6,000 homes. That same year, their CEO made $16 million in salary and bonuses. Edison’s victims want full and fairly compensation, not a discount program, and this extension is not going to save them.”
The tension between the alternatives has left many survivors with a difficult choice to apply for the compensation plan money or risk time in court, which could also take time from actually rebuilding or moving back to Altadena.
The Southern California Edison Altadena Rebuild & Community Hub at 2680 Fair Oaks Ave in Altadena on Sep. 17, 2026. (Contributing Photographer, Connor Terry)
Underlying SCE’s urgency appears to be the utility’s need for certainty. The decision to extend the deadline – and to make it a hard stop – aligns with the Rosemead-based utility’s push on lawmakers to codify in state law how wildfire liability is distributed in the state.
While SCE said it needs more time to prepare for legal battles in court, the utility’s leadership have been calling for a special legislative session as soon as possible. Wildfire liability reform failed during the last regular legislative session, but Pizarro said the hope is for a December session around when the new class of lawmakers are sworn in next month.
Pizarro likened the urgency of wildfire liability reform and his company’s debt and credit rating situation to someone buying a home with a credit score of 800 compared to one of 500.
He said SCE has the lowest possible investment rate credit rating with one of the rating agencies, Fitch, warning of a multi-notch downgrade if there isn’t action soon.
“Action meaning new legislation that would provide … something that would stabilize the rules set around how wildfire liability is managed in the state,” Pizarro said after a recent community town hall.
Executives shared on SCE’s latest earnings call that the current pricing of the company’s debt in the market will cost customers an extra $300 million next year. That cost would increase, Pizarro said, should SCE be downgraded to non-investment grade.
“We do have confidence that in the end, I don’t know how long it might take, maybe it takes a year, maybe it takes two years,” Pizarro said. “The meter’s spinning all along in terms of customer cost, but we think that ultimately California policymakers will take action here because this is just so important to how you manage the world’s fourth largest economy.”
As of Tuesday morning, SCE has received more than 6,300 claim submissions representing more than 19,000 individuals, trusts and legal entities. Southern California Edison has extended more than 3,500 offers totaling about $1.2 billion.
To date, SCE has paid almost 5,000 claimants, totaling $700 million.
“Our survivor community has had so much stressful responsibility thrust on them,” Arnzen said. “We need to continue to find ways to relieve any unnecessary added stress and move forward with compassion and grace toward these amazing but challenged survivors.”