Mexico’s Federal Electricity Commission (CFE) announced plans to recover 290MW of generation capacity between 2026 and 2028 and execute over MX$1.56 billion in transmission and distribution investments in Baja California Sur. Because the state operates on an isolated grid facing seasonal demand peaks and fuel transport constraints, these upgrades directly impact electricity reliability for tourism operators, commercial developers, and industrial investors. 

 

Mexico’s Federal Electricity Commission (CFE) reported progress on infrastructure maintenance, generation recovery, and grid expansion in Baja California Sur during a follow-up meeting with state authorities and business representatives on Nov. 25, 2026. The program outlines the recovery of 290MW of generation capacity between 2026 and 2028 alongside over MX$1.56 billion in transmission and distribution investments.

Lorena Hinojosa, Investment Coordinator of Baja California Sur, recognized the utility’s responsiveness to private sector requests and reiterated the business community’s willingness to collaborate on actions aimed at reinforcing electricity supply reliability across the state, according to the CFE press release. 

Baja California Sur operates on an isolated electrical system disconnected from Mexico’s National Interconnected System, creating operational vulnerabilities during summer demand peaks and logistical challenges for transporting conventional fuels. The state-level working group, organized under the CFE Conectada Contigo strategy led by Emilia Calleja, Director General, CFE, tracks preventive maintenance and grid expansion ahead of the summer 2027 peak demand season.

These regional upgrades align with CFE’s broader national infrastructure roadmap. CFE’s 2026–2030 Expansion Plan comprises 32 electricity transmission projects and four generation initiatives—including the 100MW Termosolar I El Crucero and 50MW Termosolar II Comondú projects in Baja California Sur—to diversify generation technologies and expand grid capacity. Furthermore, CFE launched a tender in November 2026 for the 60MW Oasis hybrid project in Mulegé, Baja California Sur, integrating solar generation, battery energy storage systems, and green hydrogen to stabilize the isolated grid.

In the generation segment, CFE scheduled plant rehabilitation and maintenance works to recover approximately 290MW of capacity between 2026 and 2028. Within this schedule, the Los Cabos power plant is projected to reach an operational availability rate above 96% during 2027.

For the transmission network, CFE detailed eight projects representing an investment of MX$896 million aimed at increasing transformation capacity and voltage support, with completion dates scheduled between June and December 2027. These works build upon the recently completed Olas Altas Banco 2 and Buena Vista Banco 1 substations, which supply 150,000 users and support commercial and tourism operations in the state.

In the distribution segment, CFE executed MX$155 million during 2026 for network expansion, modernization, and electrification works. CFE also allocated an additional MX$509 million to construct a substation in Los Cabos, expand capacity at the Villa Constitución Banco 1 substation in Comondú, execute 14 grid modernization projects, and complete 193 rural electrification works.

By pairing generation maintenance with substation and distribution upgrades, CFE aims to prevent supply interruptions during peak consumption periods and accommodate commercial, hospitality, and residential growth across Baja California Sur’s main economic corridors.