The rapidly growing demand for electricity, which has been driven largely by data center development, could create serious electricity reliability issues across the state and the region.
That’s the finding of an independent analysis conducted by Synapse Energy Economics that was released Monday by the Pennsylvania Public Utility Commission.
The analysis examined whether sufficient electric resources will be available to reliably serve customers as demand grows, and existing generation retires.
It found that based on the current load forecast from regional power grid operator PJM, the regional grid will fail to meet PJM’s reliability planning standard from 2027 through 2030.
“Pennsylvania is at an energy crossroads,” said PUC Chairman Steve DeFrank. “Data center development brings significant opportunities, but that growth cannot come at the expense of the families and businesses that already depend on reliable and affordable electric service. This analysis sends a clear warning: electricity demand and supply are moving out of balance, and the status quo is not sustainable. We need urgent action at PJM and a broader Pennsylvania energy strategy that makes sure our supply of electricity keeps pace with demand.”
According to the commission, PJM plans the regional electric system around a longstanding reliability standard designed to limit potential electricity shortages to approximately one event every 10 years.
The Synapse analyses show how dramatically that risk could change if electricity demand grows faster than available supply.
Under what it described as the most likely scenario based on the current environment, the reliability risk in 2030 is nearly six times PJM’s planning standard.
Under a more severe scenario combining higher electricity demand with constrained development of new generation, the analysis projects an the potential for more than 13 loss-of-load events per year starting in 2030 – compared with the traditional planning standard of one event every 10 years.
In the study’s severe scenario, projected new data center demand across PJM between 2029 and 2030 alone exceeds the current annual electricity demand of the entire state of Pennsylvania.
“Time matters,” DeFrank said. “The changes highlighted in this report are not decades away. The reliability pressures emerge during the next several years, and the decisions being made now will determine how prepared we are to meet them.”
He noted that the commission has already taken several steps to address large-load growth and protect existing customers.
In May, the PUC established a model large-load tariff designed to ensure that customers requiring 50 megawatts or more of electricity bear the costs they add to the electric system rather than shifting those costs to other ratepayers.
The commission is also implementing Act 45 of 2025, which provides an additional layer of accountability for Pennsylvania utility load forecasts submitted to PJM – an increasingly important “double check” as data center proposals drive projections of future electricity demand.