Harrisburg, Pa. — Large new electricity users such as data centers that have not secured enough new power capacity to support their demand would be curtailed before other customers when the grid needs to cut load to stay reliable, under a proposal the Pennsylvania Public Utility Commission advanced Oct. 1.

The commission voted 4-0 to approve a Tentative Order seeking public comment on proposed changes to how Pennsylvania electric utilities prepare for and respond to periods of tight electricity supply, including new procedures for electric distribution companies addressing large loads such as data centers, according to a PUC release.

The commission is also proposing that electric distribution companies not classify large loads such as data centers as critical loads exempt from curtailment during pre-emergency or emergency events.

What utilities would have to do

PJM Interconnection, the regional grid operator serving Pennsylvania, 12 other states and the District of Columbia, has proposed a new Interim Resource Adequacy Service, or IRAS, intended to help manage periods when available electric resources may not be sufficient to reliably meet demand, according to the release.

Under the PUC’s Tentative Order, Pennsylvania electric distribution companies would prepare for those situations by identifying large loads in their service territories and establishing procedures for responding when PJM calls for load reductions. Among the proposals, utilities would be required to:

Develop and maintain a registry of large loads within their service territories, giving utilities, PJM and the PUC better information to prepare for rapidly growing electricity demand.Establish procedures for identifying and notifying large-load customers that may be required to reduce their electricity use when PJM determines additional load reductions are needed to maintain reliability.Establish procedures to reduce eligible new large loads that have not secured sufficient new electric capacity before shedding load from other customers during an IRAS event.Update pre-emergency and emergency procedures so that large loads such as data centers are not classified as critical load exempt from curtailment during those events.

The commission is seeking public and stakeholder input on those proposals, along with other steps that may be appropriate as Pennsylvania and PJM respond to what the PUC called “unprecedented load growth.”

Why the PUC acted

The Oct. 1 vote builds on a Sept. 10 motion offered by PUC Vice Chair Barrow and unanimously approved by the commission, directing PUC staff to outline proposed updates that Pennsylvania’s electric distribution companies must make to their emergency electric load-control procedures, according to the release.

It also follows an independent analysis commissioned by the PUC that warned rapidly growing electricity demand — driven largely by data center development — could create serious reliability risks if electric supply does not keep pace. Under the study’s reference scenario, the regional grid fails to meet PJM’s reliability planning standard from 2027 through 2030, with modeled reliability risk by 2030 nearly six times that standard, the release said.

Other PUC work on large loads

The PUC described the Oct. 1 action as one part of a broader series of commission initiatives on data centers and other large-load customers. Those include the commission’s model tariff for large-load customers, designed to help ensure that customers requiring 50 megawatts or more of electricity bear the costs they add to the electric system rather than shifting those costs to other ratepayers; implementation of Act 45 of 2025, which strengthens PUC oversight of utility load forecasts submitted to PJM; and commission actions addressing PJM’s proposed Reliability Backstop Procurement and Interim Resource Adequacy Service.

The PUC is also examining how costs associated with large computational loads are allocated, with a technical conference scheduled for Nov. 17 to gather input from utilities, consumer advocates, large-load customers and other stakeholders, according to the release.

How to comment

The Tentative Order is to be published in the Pennsylvania Bulletin, which begins a formal public comment period. Interested parties will have 30 days after publication to submit comments, followed by an additional 15 days for reply comments, according to the release. The release did not give a publication date.

After reviewing comments, the commission anticipates considering a Final Order at its Jan. 28, 2027, public meeting, directing Pennsylvania electric distribution companies to file updated procedures. The proposals and the commission’s questions for public comment are listed under PUC docket M-2026-3064961.


Success! An email has been sent to with a link to confirm list signup.

Error! There was an error processing your request.

Get Our Free Newsletters

Never miss a headline with NorthcentralPa.com newsletters.

Sign Up Today!

Morning Headlines: Would you like to receive our daily morning newsletter? 

Afternoon Update: What’s happening today? Here’s your update!

Daily Obits: Get a daily list straight to your email inbox.
 


Keep your news local

Access to independent, local news is important, do you agree?

We work hard to deliver timely, relevant news, for free. 100% of your contribution to NorthcentralPa.com goes directly to helping us cover news and events in the region.

Thank you for saying that local news matters!


Donate Today