Transportation projects are often the most visible and significant public works projects in our communities. In many ways, that makes every driver a transportation expert. For those of us working daily on transportation projects, that is what makes our jobs so rewarding. Transportation is important to our friends, neighbors, colleagues and the public we serve. That said, major transportation projects can be difficult to follow or understand if you do not work in that industry or make it a priority to learn the nuances of infrastructure. Is it reasonable to expect Maryland residents to know the difference between a continuous truss bridge and a cable-stayed bridge? No. Do most readers know that typical infrastructure projects begin with years of planning and design before any construction ever scratches the surface, or riverbed? Probably not.
And that’s OK.
On a mega infrastructure project like the Francis Scott Key Bridge rebuild, it’s the responsibility of those managing the project to explain the facts, processes and progress in ways that communities can understand.
To set the record straight, the new Key Bridge is under construction, and work will continue while the existing contractor finishes its contractual obligations and new contractors are brought on.
The Moore-Miller administration has been fully transparent on the activities going on with the rebuild, from construction to securing federal funds and permits to shifts in contractors and procurement progress. The newly launched dashboard on KeyBridgeRebuild.com is an excellent tool to see progress, but so much more is happening to help educate the public. The Maryland Transportation Authority, or MDTA, regularly schedules tours for media, project stakeholders, elected officials and federal partners to show progress from a viewpoint that the public cannot safely access.
Are you following the project on Facebook, signed up for the newsletter and regular e-blasts or seeing the team at community events? If not, you may be getting inaccurate information on the project from someone who still doesn’t know what type of bridge the new Francis Scott Key Bridge will be.
But what about design; is that complete? Not quite, and there is a reason for that.
Most mega projects take five to seven years of planning and design before construction even begins. The Key Bridge rebuild is an emergency project and is accomplishing both planning and design work while simultaneously beginning construction. It’s easy to say another bridge was built quicker, but that doesn’t consider the years, sometimes decades, of planning and design work that happened before construction began. Design will reach 100% completion once the new contractors are selected.
It’s safe to say the Key Bridge rebuild is not a typical construction project.
So how will construction happen? The new Key Bridge will be constructed in three sections: the south land approach, the north land approach and the main span with the marine approaches. The south and north land approaches will begin construction in spring 2027, after the production pile driving wraps up. Construction of the cable-stayed main span and marine approaches will begin next summer after a thorough procurement process to ensure the best team to do the job is selected. All this information can be easily accessed and followed at KeyBridgeRebuild.com.
And finally, demolition. Many ask, why are parts of the original bridge still standing? Fair question. The demolition contract for the remaining pieces of the original bridge will be awarded later this fall. While this award is a significant milestone, the truth is those piers are not interfering with construction progress. The new bridge’s final alignment is 260 feet east of where the original bridge stood. In fact, it would have cost more to mobilize the specific marine-based equipment needed to demolish those piers during the same time as mechanical land demolition was successfully completed.
The point is, while those piers over water remain, construction continues.
Since the beginning, Maryland has been and will continue to be transparent to keep our stakeholders, customers and communities informed every step of the way. The Key Bridge rebuild project is highly visible, and transparency is non-negotiable.
The rebuild project is deeply rooted in the needs of our local communities and seeks to enhance daily life, strengthen connections, facilitate the movement of people and goods across the country and deliver a modern bridge that will serve Marylanders for generations to come.
Bruce Gartner is the executive director of the Maryland Transportation Authority.