{"id":130094,"date":"2026-11-10T00:41:18","date_gmt":"2026-11-10T00:41:18","guid":{"rendered":"https:\/\/www.europesays.com\/thestates\/130094\/"},"modified":"2026-11-10T00:41:18","modified_gmt":"2026-11-10T00:41:18","slug":"google-pairs-wyoming-data-center-with-702-mw-of-fuel-cells","status":"publish","type":"post","link":"https:\/\/www.europesays.com\/thestates\/130094\/","title":{"rendered":"Google Pairs Wyoming Data Center With 702 MW of Fuel Cells"},"content":{"rendered":"<p>Google will build its first Wyoming data center, a\u00a0$17 billion campus in Cheyenne, and the announcement arrived with much of the power supply already under contract. American Electric Power (AEP) will serve the site from a 702-megawatt (MW)\u00a0fuel cell plant running on natural gas, and gas generators operated by\u00a0Tallgrass Energy\u00a0and\u00a0Black Hills Energy\u00a0will add supply, according to\u00a0<a href=\"https:\/\/blog.google\/innovation-and-ai\/infrastructure-and-cloud\/global-network\/wyoming-data-center\/\" rel=\"noopener noreferrer nofollow\" target=\"_blank\">Google&#8217;s announcement<\/a>.<\/p>\n<p>Google calls the fuel cell development the largest of its kind planned and says carbon capture and storage will keep a large majority of the plant&#8217;s emissions out of the atmosphere. The company&#8217;s announcement gives no capture rate and no figure for the campus&#8217;s total electricity load. Project details in this piece come from announcements by Google, AEP and Intersect, a Google subsidiary.<\/p>\n<p>AEP Owns the Cheyenne Plant and Sells to Google for 20 Years<\/p>\n<p>AEP set out the financing in its\u00a0<a href=\"https:\/\/www.prnewswire.com\/news-releases\/aep-advances-innovative-energy-solution-for-google-with-702mw-of-bloom-fuel-cells-302907658.html\" rel=\"noopener noreferrer nofollow\" target=\"_blank\">Oct. 14 release<\/a>. The utility plans to spend about\u00a0$4 billion\u00a0on the project, which will sell its output to Google under a\u00a020-year\u00a0power purchase agreement. The plant will be held by Cheyenne Fuel Cell LLC, owned about\u00a092%\u00a0by AEP, with funds advised by Basalt Infrastructure Partners holding the rest. Construction is due to begin in 2026, and AEP expects full operation by the end of 2028.<\/p>\n<p>The\u00a0Bloom Energy\u00a0units generate electricity through an electrochemical reaction, without burning the gas. Bloom has taken the same technology to other AI developers, including a\u00a0<a href=\"https:\/\/www.environmentenergyleader.com\/articles\/2259-fuel-cells-power-brookfields-ai-factories\" rel=\"nofollow noopener\" target=\"_blank\">$5 billion alliance with Brookfield to build data centers on onsite fuel cells<\/a>. Carbon dioxide captured at Cheyenne is slated for Tallgrass&#8217;s Eastern Wyoming Sequestration Hub. Google also plans a front-end engineering and design study on fitting capture equipment to Tallgrass&#8217;s combined-cycle turbines, an evaluation that stops short of a commitment to install it.<\/p>\n<p>Google says it will pay for\u00a0100%\u00a0of the power the campus uses and cover infrastructure needs driven directly by its growth. The buildings will be air-cooled to limit demand on local water. The company expects the project to generate hundreds of millions of dollars in property taxes for Laramie County and Laramie County School District 1, and it is forming a community council with its energy partners to take up local concerns about data center growth.<\/p>\n<p>In Texas, Google Owns the Generation Developer<\/p>\n<p>The arrangement looks different in the Texas Panhandle. In June, Google and Intersect\u00a0<a href=\"https:\/\/blog.google\/innovation-and-ai\/infrastructure-and-cloud\/global-network\/meitner-energy-center\/\" rel=\"noopener noreferrer nofollow\" target=\"_blank\">announced the Meitner Energy Center<\/a>\u00a0in Gray and Roberts counties, a data center built alongside more than\u00a01 gigawatt\u00a0of wind, solar and battery storage. Google closed its purchase of Intersect in March, so the load and the generation sit under one parent.<\/p>\n<p><a href=\"https:\/\/www.intersect.com\/news\/google-and-intersect-deepen-texas-roots-with-new-data-center-and-energy-investments-in-gray-and-roberts-counties\" rel=\"noopener noreferrer nofollow\" target=\"_blank\">Intersect says<\/a>\u00a0clean energy will cover most of the site&#8217;s power from the first day, with on-site gas firming a smaller share. Google expects the setup to reduce the need for new supply from the local grid. Developers have been weighing electrical capacity ahead of land when\u00a0<a href=\"https:\/\/www.environmentenergyleader.com\/articles\/45159-how-powered-land-is-changing-data-center-site-selection\" rel=\"nofollow noopener\" target=\"_blank\">choosing data center sites<\/a>, which has pushed more of them toward onsite generation.<\/p>\n<p>Michigan Attorney General Seeks Rehearing on DTE Contract<\/p>\n<p>In Michigan, the cost protections are written into a utility contract. On Oct. 1, the Michigan Public Service Commission (MPSC)\u00a0<a href=\"https:\/\/www.michigan.gov\/mpsc\/commission\/news-releases\/2026\/10\/01\/mpsc-approves-dte-electric-google-data-center-and-contracts-protects-customers-from-project-cost\" rel=\"noopener noreferrer nofollow\" target=\"_blank\">approved special contracts<\/a>\u00a0between DTE Electric and Google for a data center in Van Buren Township, Wayne County, in Case No. U-22058. The supply agreement runs\u00a020 years, against the five-year term normally required under DTE&#8217;s large-load rate. Google must pay for at least\u00a080%\u00a0of its contracted demand, compared with 50% to 65% under the general rate, and would owe at least\u00a015 years\u00a0of minimum monthly charges if it cancels early. Payment floors and collateral terms of this kind now show up in\u00a0<a href=\"https:\/\/environmentenergyleader.com\/stories\/large-load-tariffs-carry-contract-terms-like-long-term-debt,132751\" target=\"_self\" rel=\"nofollow noopener\">large-load tariffs in a growing number of states<\/a>.<\/p>\n<p>A second agreement has Google paying for up to\u00a01,600 MW\u00a0of renewable generation and\u00a0480 MW\u00a0of battery storage, which DTE will develop, own and operate. The contracts also require credit and collateral in case the data center shuts down early. DTE projects the deal will cut costs for its other customers by\u00a0$1.7 billion\u00a0over the 20-year term.<\/p>\n<p>Attorney General Dana Nessel\u00a0is contesting that projection. Her office filed a\u00a0<a href=\"https:\/\/www.michigan.gov\/ag\/news\/press-releases\/2026\/10\/30\/ag-nessel-challenges-mpsc-approval-of-dtes-google-data-center-contracts\" rel=\"noopener noreferrer nofollow\" target=\"_blank\">petition for rehearing<\/a>\u00a0on Oct. 30 arguing that the commission let DTE net costs against benefits across the full contract term, a method the petition says leaves other customers subsidizing the data center from 2035 through 2038. The filing also objects to a cap on collateral owed by Google and parent Alphabet and says DTE has not accounted for transmission costs. Nessel wants costs and benefits reconciled every year, and she asked the commission to reject the contracts if it will not adopt her recommendations. She took a similar fight over DTE&#8217;s Saline Township data center contracts to the state Court of Appeals in April,\u00a0<a href=\"https:\/\/www.michigan.gov\/ag\/news\/press-releases\/2026\/04\/17\/ag-nessel-files-appeal-of-mpsc-approval-of-dtes-saline-data-center-contracts\" rel=\"noopener noreferrer nofollow\" target=\"_blank\">after the commission approved them<\/a>.<\/p>\n<p>Construction Dates and a Pending Petition<\/p>\n<p>AEP has said construction on the fuel cell plant will begin in 2026. In Michigan, Nessel&#8217;s petition is pending before the commission, and DTE expects to begin serving the Van Buren Township site in December 2027, reaching full load by December 2028.<\/p>\n","protected":false},"excerpt":{"rendered":"Google will build its first Wyoming data center, a\u00a0$17 billion campus in Cheyenne, and the announcement arrived with&hellip;\n","protected":false},"author":2,"featured_media":130095,"comment_status":"","ping_status":"","sticky":false,"template":"","format":"standard","meta":{"footnotes":"","_share_on_mastodon":"0"},"categories":[51],"tags":[27327,40401,4610,17840],"class_list":["post-130094","post","type-post","status-publish","format-standard","has-post-thumbnail","category-wyoming","tag-aep","tag-bloom-energy","tag-google","tag-wyoming"],"share_on_mastodon":{"url":"https:\/\/pubeurope.com\/@us\/117589369404476783","error":""},"_links":{"self":[{"href":"https:\/\/www.europesays.com\/thestates\/wp-json\/wp\/v2\/posts\/130094","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.europesays.com\/thestates\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.europesays.com\/thestates\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.europesays.com\/thestates\/wp-json\/wp\/v2\/users\/2"}],"replies":[{"embeddable":true,"href":"https:\/\/www.europesays.com\/thestates\/wp-json\/wp\/v2\/comments?post=130094"}],"version-history":[{"count":0,"href":"https:\/\/www.europesays.com\/thestates\/wp-json\/wp\/v2\/posts\/130094\/revisions"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.europesays.com\/thestates\/wp-json\/wp\/v2\/media\/130095"}],"wp:attachment":[{"href":"https:\/\/www.europesays.com\/thestates\/wp-json\/wp\/v2\/media?parent=130094"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.europesays.com\/thestates\/wp-json\/wp\/v2\/categories?post=130094"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.europesays.com\/thestates\/wp-json\/wp\/v2\/tags?post=130094"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}