RAWLINS — A major visible step in the Edinburgh Street Reconstruction Project is underway: crews have begun pouring curb and gutter, driveway entrances, and sidewalks in the first two sections at the south end of the project.

As concrete work progresses, the city of Rawlins is asking residents to please help protect the new improvements. Do not drive on newly poured driveway entrances for seven days. Please leave barriers or curing materials in place until crews remove them.

For the first month, please avoid unusually heavy loads on new driveway concrete, such as loaded utility trailers, campers or RVs, moving trucks, or other heavy residential vehicles. If you are unsure, please contact Public Works at 307-328-4599.

According to the American Concrete Institute, it is best not to apply deicing salts through one winter. This winter, residents can also help protect new concrete by using sand for traction instead. Also, please take care when shoveling or plowing so metal edges do not scrape or gouge the new surface.

Edinburgh/Inverness Intersection Remains Closed

The Edinburgh/Inverness intersection remains closed while crews work through issues involving sanitary sewer and manholes in the intersection. These issues have taken longer to resolve than anticipated and have prevented the intersection from reopening. Drinking water work is following closely behind the sewer work.

Once the sewer and manhole issues are resolved, crews expect work through the intersection to move relatively quickly.

Traffic entering Highland Hills should continue to use the northern entrances through Aberdeen Avenue or Pettigrew Boulevard. Please follow posted detours and use caution around the construction area. We will provide an update as soon as we have a clearer timeline for reopening the intersection.

Current Project Status

The latest Status Tracker shows continued progress across the seven sections of the project:

  • Storm and groundwater mitigation: 4 sections completed; 1 in process.
  • Sanitary sewer: 6 sections completed; 1 in process.
  • Drinking water: 5 sections completed; 1 in process.
  • Curb, gutter, driveway entrances and sidewalks: 2 sections in process.
  • Street pavement: The first section is currently anticipated around the end of September.