The 350 MW/1.4 GWh Albatross BESS in Germany has reached financial close, which GIGA Storage, a Netherlands-based energy storage company, completed on 23 October 2026. Seven international banks, among which are ABN AMRO, ING and SMBC, are providing the debt of €260 million (~ $290.85 million). The plant is to be built near Neuenkirchen in Lower Saxony, Germany, and it will be the first project that GIGA Storage has in the country. CATL will be responsible for the engineering, construction and maintenance of the plant, and the construction is to start in early 2027. The plant will be connected directly to the 380 kV Merzen substation of Amprion, and it is expected to begin operation in early 2029. That financing has taken the storage capacity that GIGA Storage has under construction in the Netherlands, Belgium and Germany to approximately 1.4 GW/5.6 GWh.