Network Rail has published its travel plan for the Birmingham New Street Christmas closure, with no trains December 24–28 and a £6.4m Soho junction and track renewal planned alongside.
A CrossCountry train at Birmingham New Street during snowfall. Photo: CrossCountry.
No trains will run to, from or through the station from Thursday, December 24, through Monday, December 28, 2026, and a full timetable returns on Tuesday, December 29. Christmas timetables and operator-by-operator alternatives are now available.
For passengers, the shutdown changes travel on three days: Christmas Eve, Sunday, December 27, and the bank holiday on Monday, December 28. As every year, the station has no trains on Christmas Day or Boxing Day. Network Rail suggests moving trips to dates outside the closure where possible but expects trains on either side of it to be more crowded than usual. Birmingham Snow Hill and Birmingham Moor Street will also be busier, and Christmas Eve services there will end early, as they do annually.
Overhead line renewal and Soho track work
The closure lets Network Rail start a £13m program to renew the overhead line equipment on the approaches to and through New Street. Much of that wiring was installed in the 1960s, and the company says replacing it will cut the risk of faults and improve long-term reliability. This Christmas is the first of three phases, with further work planned for Christmas 2027 and Christmas 2028.
The closure also carries other projects. Network Rail is spending £6.4m to replace aging junction equipment and renew 800 meters of track at Soho. Track will also be renewed on the line between Birmingham and Sandwell and at Berkswell, between Birmingham and Coventry. At Berkswell, crews will install a new turnout linking the existing railway to new sidings, which will handle materials for later stages of HS2 construction. According to Network Rail, combining the jobs keeps overall disruption down and reduces the need to disrupt services again later.
Mark Goodall, route director for Network Rail’s Central route, explained the timing:
“We’re using the annual Christmas Day and Boxing Day shutdown to get as much essential work done as possible and minimise the overall disruption to passengers.”
Operator alternatives during the shutdown
Five operators have set out alternatives. Avanti West Coast will run an amended timetable without calling at New Street, with replacement buses to Wolverhampton and to Birmingham International. CrossCountry trains will be amended or diverted to run between Coleshill Parkway and Stansted Airport, Nottingham and Cardiff Central, Edinburgh and Plymouth, and Manchester Piccadilly and Bournemouth, while buses connect New Street with Coleshill Parkway via Water Orton, with Worcestershire Parkway, and with Tamworth via Wilnecote.
London Northwestern Railway services from London Euston and Northampton will start and finish at Birmingham International on December 27 and 28. Separate engineering on the West Coast route closes the line between Northampton and Rugby via Long Buckby from December 27, 2026, to January 1, 2027, with buses in place of trains. The operator’s Crewe and Liverpool Lime Street trains will run only from Wolverhampton, at reduced frequency. From there, passengers can take a train to Sandwell & Dudley, a bus to Smethwick Galton Bridge and a train to Birmingham Snow Hill, with up to five trains an hour on that last leg.
West Midlands Railway will run no trains on the Cross City corridor between Lichfield Trent Valley or Four Oaks and Bromsgrove or Redditch, nor between New Street and Kings Norton via Kings Heath, with buses covering both. Its trains to Worcester Foregate Street, Great Malvern and Hereford will be diverted to start and end at Birmingham Snow Hill. Routes toward Rugeley Trent Valley, Shrewsbury and Walsall will be cut back to Wolverhampton or Sandwell & Dudley at reduced frequency. Transport for Wales will not run between Wolverhampton and Birmingham International.
How each operator runs during the Birmingham New Street closure, Dec. 24–28, 2026
Trains during the closure
Replacement buses
Chiltern services, bus tickets and station access
Transport for West Midlands says Chiltern Railways will keep serving Moor Street and Snow Hill, and that train tickets for local journeys on the Camp Hill and Cross City lines will be accepted on National Express buses.
The station building will stay open throughout, giving access to Grand Central and the city center. The assisted travel lounge and toilets remain available with staff on site, but the Avanti West Coast first class lounge will close. Queuing systems will be used at busy times to help passengers reach replacement buses and onward connections.
How New Street fits into Network Rail’s Christmas 2026 works
Birmingham New Street is one of the key sites in Network Rail’s £152 million program of Christmas and New Year 2026 projects, alongside London Paddington and Huddersfield. Several of those jobs keep lines shut for longer. Great Western Railway trains will not reach Paddington until January 4, 2027, the Great Eastern Main Line at Forest Gate will close for 10 days from Christmas Day, and work around Huddersfield will disrupt services until February 1, 2027. Office of Rail and Road figures put New Street as Britain’s busiest station outside London in the year to March 2025, with 36.6 million entries and exits.
Christmas 2026 engineering closures highlighted by Network Rail
Closure period
Main work