Bristol Brabazon station will open to passengers on Monday, November 23, bringing regular passenger trains back to the Henbury Line near Bristol, England, for the first time since 1964.

Bristol Brabazon sign beside a new concrete platform edge and tracks, with construction work and apartment blocks behindA Bristol Brabazon sign next to the new station platform and tracks. Photo: West of England Mayoral Combined Authority

Great Western Railway (GWR) will start with one train an hour to Bristol Temple Meads, which links the station to the wider rail network. The first departure leaves for Temple Meads at 07:10 on opening day. The West of England Mayoral Combined Authority, which confirmed the opening date on November 6, said GWR plans to increase frequency as the Aviva Arena and further development at Brabazon progress.

The station stands on the former Filton airfield, where the Brabazon new town is taking shape, and will serve both the new community and the 20,000-capacity arena. It is the first of two new stations planned in the West Innovation Arc Mayoral Development Zone.

What GWR’s track access application says about the service

The Office of Rail and Road directed Network Rail and GWR on October 30 to enter an access agreement that lets GWR run trains between Bristol Brabazon and Bristol Temple Meads every day of the week, with no more than one train per hour in each direction. GWR’s original application, published by the regulator in November 2025, described the Henbury line as freight-only. It proposed extending all Monday-to-Saturday trains between Bristol Temple Meads and Filton Abbey Wood to the new station, then called North Filton, and adding trains for longer operating hours and a Sunday service.

What opens on November 23 and what follows by 2028

Opening day completes the first construction phase. Passengers will find accessible parking, cycle storage and an accessible bridge between the two platforms, with more car parking for station users in the center of Brabazon. The station opens unstaffed. A staffed ticket office will follow on the ground floor of The Interchange, an eight-story office building now under construction by YTL Construction UK.

Network Rail plans a second construction phase to add capacity ahead of the arena. The combined authority says that work continues through 2028 in collaboration with YTL UK and brings a second footbridge with ramps, a staffed ticket office with ticket gates, toilets, a ticket sales desk and staff facilities. A new public square will handle the large numbers of passengers expected to travel to the Aviva Arena and the surrounding area. The m4 metrobus route also serves the station, linking it with Cribbs Causeway, Bristol Parkway and nearby communities.

Marcus Jones, route managing director for Network Rail’s Great Western Route, said of the construction timeline:

“Work began in July 2025 and, just 16 months later, we’re all set to welcome the first passengers to Bristol Brabazon.”

Bristol Brabazon station: what is in place on November 23 and what the second phase adds through 2028. Source: West of England Mayoral Combined Authority, November 6, 2026

Feature
At opening (first phase)
Second phase (through 2028)
Crossing between platforms

Accessible bridge linking the two platforms Second footbridge, with ramps Staffing and tickets

Unstaffed station Staffed ticket office with ticket gates and a ticket sales desk, on the ground floor of The Interchange Passenger facilities

Accessible parking, cycle storage, car parking for station users in central Brabazon Toilets and a new public square sized for Aviva Arena crowds Staff facilities

Not stated Staff facilities included

Funding and the wider West of England station program

Network Rail and partners delivered the station. The Mayoral Combined Authority has committed £50 million to both construction phases and the connection to the network. YTL UK has invested more than £24 million in the area through contributions via South Gloucestershire Council and direct delivery on site, and plans a further £80 million over the next decade.

Bristol Brabazon is one of five new stations planned across the West of England over the next two years under a wider £600 million rail connectivity investment, and it follows the recent openings of Portway Park & Ride and Ashley Down. Mayor Helen Godwin named Charfield, Portishead, Pill and Henbury as the other new stations in progress. The combined authority expects services on the Portishead line, now being restored, to connect directly onto the Henbury Line from winter 2028/29. Network Rail gives that window for the Portishead–Bristol Temple Meads service and describes a later extension through to Bristol Brabazon without a separate date.

GWR’s Growing Places research links much of the expected economic gain around its stations to Brabazon. The report estimates that occupation of new developments near selected GWR stations will add a further £2.92 billion a year in economic output over the next five to 10 years, with £2.17 billion a year of that tied to the Bristol Brabazon masterplan.