UKRAINE: Autostrada has completed the tunnel under European Union Avenue on Kyiv’s Vynohradar metro extension and aims to reopen the avenue by Christmas, past its December 1 closure deadline.
An excavator works at the bottom of a metro construction pit braced with steel pipe struts. Photo: Autostrada
The contractor reported the result in a November 23 construction update from Autostrada, saying crews are now fitting out engineering networks on the section and that about 80% of the planned work on this stretch is done. The update does not name the type of tunnel. In early October, Autostrada said its work within European Union Avenue centered on concreting the two-level running tunnel between the future Varshavska and Mostytska stations.
Utility relocation and road works on European Union Avenue
Storm and domestic sewers and a drainage system are still under construction on the section. In parallel, Autostrada is moving water and heating mains, gas pipelines of various pressures, high-voltage power cables and telecommunications cable ducts out of the work zone.
Where relocation is finished, Autostrada road crews have started restoring the carriageway and sidewalks. On the Svobody Avenue side of European Union Avenue, they are milling the worn asphalt and replacing the structural base layers of the pavement. A new stormwater collector is being laid by microtunnelling: the NIKA machine has completed 460 meters of the planned 750 meters, up from 180 meters reported in early October.
TBM Victoria and the left running tunnel to Mostytska
Assembly of the main units and systems of the tunnel boring machine Victoria continues, with more than 70% of the new Herrenknecht equipment already delivered to the site. After assembly and commissioning, Victoria will bore the left running tunnel between Syrets and Mostytska stations. Autostrada says it works around the clock.
Autostrada put its investment in TBM Victoria at more than €15 million in October. It bought the new machine after a Herrenknecht inspection found that nearly 99% of the equipment on Galina, a tunnel boring machine Autostrada had acquired from previous owners, was unfit for further use. The company has also started making reinforced concrete lining segments at its own plant in Herrenknecht-made moulds, with seven segments forming each ring. It estimates the machine can install 8–10 rings a day, or about 10–12 meters of tunnel.
Interior of a concrete metro tunnel with cable brackets mounted on the wall. Photo: Autostrada
The 3.78 km section and the European Union Avenue closure
The Syretsko-Pecherska Line extension covers a 3.78 km section with two new stations, Mostytska and Varshavska (working name Prospekt Pravdy), and a forked extension toward the future Vynohradar station. The Syrets–Mostytska section is bored, while the two-level monolithic tunnels between Mostytska and Varshavska are built by cut-and-cover. Autostrada reported more than 750 meters of these two-level tunnels in place in December 2025.
The road closure covers European Union Avenue between Vasyl Poryka Avenue and Svobody Avenue. The Kyiv City State Administration Department of Transport Infrastructure said in April that the restriction, originally due to end on April 5, 2026, had been extended to December 1, 2026 after the work schedule was revised.
European Union Avenue closure and Vynohradar metro extension deadlines
Milestone
By November 24, 2026, the avenue had been closed for about 20 months, and Autostrada’s Christmas target falls after the extended December 1 deadline (editorial calculation from the dates shown). Dates come from the Kyiv City State Administration Department of Transport Infrastructure notices of March 2025 and April 2026, the November 23 Autostrada update and contract details published by UNN in August. No newer closure order was found as of November 24, and the start date of the 30-month contract period is not specified.
Funding for the first phase to Varshavska
Kyiv Metro told UNN in August that the first phase, from Syrets to Varshavska with part of the fork toward Vynohradar, is built under contract No. 466-ДБМ-24 of August 14, 2024, worth about UAH 13.8 billion. Completing it within the contract deadlines requires about UAH 11.57 billion from the city budget. UNN found that Kyiv’s 2026 development program allocates about UAH 1.69 billion to the Syrets–Vynohradar section, including an electric depot. Kyiv Metro said amounts for 2027–2029 will be set in later programs and that the timeline depends on the city budget and martial law, including the curfew.