GLASGOW Central Station could take “weeks” to fully reopen following the devastating fire which tore through a nearby building, an official has said.
The Scottish Fire and Rescue Service handed over control of the flame-ravaged site on Union Corner to Glasgow City Council on Thursday, four days after the devastating blaze first caught on Sunday.
The local authority confirmed that what remains of the building is to be demolished in the interests of public safety.
The fire tore through a historic building on Union Street (Image: GCC)
Nearby Glasgow Central – Scotland’s busiest train station – has avoided any major damage from the blaze, but many trains have been cancelled until further notice.
Speaking to STV News, Glasgow City Council’s head of building standards, Raymond Barlow, said Central Station cannot fully reopen until the facade of the destroyed building is demolished.
READ MORE: Union Street fire site could become ‘five-star hotel’, says Glasgow council chief
This could take weeks, he said – but was unable to put a definite timeline on the works.
STV News reports emergency demolition of the remains of Union Corner will begin on Friday and will be carried out by contractor Burnfield Demolition, which the council said would work 24/7 to complete the works.
Barlow said: “The facade needs to come down before we can consider, certainly the entrances on Gordon Street, can reopen.”
Other parts of the concourse could partially reopen, and other entrances – such as the one on Hope Street – could be used, he added.
“It is a highly dangerous situation we’re in here, everything is so very unstable,” Barlow added.
The work will be carried out by personnel in cranes above the site to avoid danger, dismantling the remains of the building stone by stone.
Two chimney stacks that remain at the southern end of the site must be brought down before any other works can begin, it is understood.
Network Rail has previously said that Glasgow Central will reopen “as soon as it is safe to do so”.