The £400,000 makeover at One Leisure gym in Huntingdon will start on June 23.
Work will begin on the changing rooms, and from July 9 work will start on the gym facilities, including building improvements and new equipment.
In order for the work to be carried out, the gym will be temporarily closed from July 9 until July 11.
From July 12, gym facilities in the ground floor area will be available at a reduced provision.
The full closure dates are listed here:
- June 23 – male and female changing rooms will close
- July 31 – male and female changing rooms will re-open
- July 9-11 – temporary gym closure for relocation of equipment
- July 12 – ground floor temporary gym re-opens
- July 12-25 – phase one of first floor refurbishment
- July 28-31 – gym closure
- July 28-August 10 – ground floor closure for refurbishment
- August 1 – re-opening of first floor gym with new equipment
- August 11 – full re-opening of gym facilities