{"id":1296114,"date":"2026-11-06T08:32:34","date_gmt":"2026-11-06T08:32:34","guid":{"rendered":"https:\/\/www.europesays.com\/uk\/1296114\/"},"modified":"2026-11-06T08:32:34","modified_gmt":"2026-11-06T08:32:34","slug":"urban-splash-hit-by-46-5m-fire-safety-bill-on-manchester-housing-blocks","status":"publish","type":"post","link":"https:\/\/www.europesays.com\/uk\/1296114\/","title":{"rendered":"Urban Splash hit by \u00a346.5m fire safety bill on Manchester housing blocks"},"content":{"rendered":"<p>The First-tier Tribunal (Property Chamber) made remediation contribution orders against five companies \u2013 Urban Splash Limited, Urban Splash Developments Limited, Urban Splash Group Holdings Limited, Urban Splash Work Limited, and Stubbs Mill \u2013 following proceedings launched in 2024 by then housing secretary Michael Gove.<\/p>\n<p>The companies, which share responsibility for the amount demanded, must pay the money to the Ministry of Housing Communities and Local Government (MHCLG) by 3 December 2026. The first-tier tribunal held that the government had \u2018reasonably\u2019 committed \u00a351.5 million towards remediation of the blocks from the Building Safety Fund, which had to be reimbursed.<\/p>\n<p>However, the tribunal reduced the remediation bill by 10 per cent to reflect the government\u2019s own failures in the building safety crisis, including shortcomings in regulation and oversight. But, it stressed this reduction was a fairness adjustment, rather than a finding that government was responsible for 10 per cent of the defects or costs.<\/p>\n<p>The seven buildings requiring remediation included the timber-clad <a href=\"https:\/\/www.howells.uk\/projects\/burton-place\" rel=\"nofollow noopener\" target=\"_blank\">Burton Place by Howells,<\/a> the Moho Building by shedkm, the <a href=\"https:\/\/www.architectsjournal.co.uk\/archive\/chips-new-islington-manchester-by-alsop-architects\" rel=\"nofollow noopener\" target=\"_blank\">Chips Building<\/a> by Alsop Architects and the Box Works. There were also issues with the Christabel House, Emmeline House and Sylvia House \u2013 a trio of 1960s towers retrofitted by\u00a0Union North Architects.<\/p>\n<p>Urban Splash had strongly disputed the suggestion that it had acted irresponsibly or had failed to comply with government guidance and had argued the government-backed work had been wasteful and went beyond what was necessary to secure fire safety.<\/p>\n<p>In a strongly worded statement issued today (5 November), a spokesperson for it was \u2018disappointed by the decision to include a number of entities which played no part in the original development of these seven buildings\u2019, adding that this illustrated \u2018the extraordinary and far-reaching consequences of the [\u2026] Building Safety Act, which allows liability to extend beyond the original developer to associated companies which played no part in the original development of the buildings concerned\u2019.<\/p>\n<p>They added: \u2018The scale of the liability identified by the tribunal is significant for a business of our size [but] throughout these proceedings, we have continued to work closely and constructively with government.\u2019<\/p>\n<p>The spokesperson, who said the company was taking legal advice on the tribunal decision, continued by saying that Urban Splash felt \u2018reassured that government and its agencies have continued to support and fund a number of Urban Splash development and regeneration projects\u2019 and that its focus was \u2018firmly on the future rather than the past\u2019.<\/p>\n<p>They added: \u2018The challenges created by the Building Safety Act are not unique to Urban Splash. This is not simply about one company. It is about finding a way in which the objectives of building safety, housing delivery and regeneration can all be achieved together.<\/p>\n<p>\u2018The outcome of the tribunal means we are now seeking to implement and work through a plan in partnership with the government, and our other stakeholders. Our priority is to protect all stakeholder interests; preserve jobs and our valuable regeneration expertise; and maintain our capacity to deliver the much-needed homes and regeneration projects in our pipeline.\u2019<\/p>\n<p>The decision also mentions that companies Shed KM Holding Limited and Shed KM Limited had paid \u00a3600,000 between them in a settlement with the government before the tribunal\u2019s final hearing began on 27 April 2026.<\/p>\n<p>Hazel Rounding, managing director at shed km, told the AJ: \u2018Shedkm Ltd and shedkm holdings were two of the seven additional respondents joined in these proceedings due to a previous single common director.<\/p>\n<p>\u2018However, we reached a settlement with the applicant before the final hearing commenced, without any admission of liability, in order to prevent any ongoing legal costs. We cannot comment on the settlement figure.\u2019<\/p>\n<p>In previous court documents, Kerry Bretherton, representing the government, had said: \u2018Those connected to the building should pay, rather than the taxpayer.\u2019<\/p>\n<p class=\"xmsonormal\">Responding to the decision Angela Rayner, Secretary of State for housing, said: \u2018I welcome this important decision, which is clear that those responsible for unsafe buildings need to pay their fair share to fix them.<\/p>\n<p class=\"xmsonormal\">\u2018We will continue in our efforts to recover taxpayer funds spent on remediation and our work to make people\u2019s homes safe.\u2019<\/p>\n<p><a href=\"https:\/\/www.architectsjournal.co.uk\/news-fa034173\/2018-predictions-will-the-profession-continue-to-be-marginalised\/\" tabindex=\"-1\" rel=\"nofollow noopener\" target=\"_blank\">2018 predictions: Will the profession continue to be marginalised?<\/a><\/p>\n","protected":false},"excerpt":{"rendered":"The First-tier Tribunal (Property Chamber) made remediation contribution orders against five companies \u2013 Urban Splash Limited, Urban Splash&hellip;\n","protected":false},"author":2,"featured_media":1296115,"comment_status":"","ping_status":"","sticky":false,"template":"","format":"standard","meta":{"footnotes":"","_share_on_mastodon":"0"},"categories":[8813],"tags":[748,348443,393,51658,4884,74595,36586,2465,102536,16,15,74832],"class_list":["post-1296114","post","type-post","status-publish","format-standard","has-post-thumbnail","category-manchester","tag-britain","tag-cladding-crisis","tag-england","tag-fire-safety","tag-great-britain","tag-grenfell","tag-legal-action","tag-manchester","tag-ministry-of-housing","tag-uk","tag-united-kingdom","tag-urban-splash"],"share_on_mastodon":{"url":"","error":""},"_links":{"self":[{"href":"https:\/\/www.europesays.com\/uk\/wp-json\/wp\/v2\/posts\/1296114","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.europesays.com\/uk\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.europesays.com\/uk\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.europesays.com\/uk\/wp-json\/wp\/v2\/users\/2"}],"replies":[{"embeddable":true,"href":"https:\/\/www.europesays.com\/uk\/wp-json\/wp\/v2\/comments?post=1296114"}],"version-history":[{"count":0,"href":"https:\/\/www.europesays.com\/uk\/wp-json\/wp\/v2\/posts\/1296114\/revisions"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.europesays.com\/uk\/wp-json\/wp\/v2\/media\/1296115"}],"wp:attachment":[{"href":"https:\/\/www.europesays.com\/uk\/wp-json\/wp\/v2\/media?parent=1296114"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.europesays.com\/uk\/wp-json\/wp\/v2\/categories?post=1296114"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.europesays.com\/uk\/wp-json\/wp\/v2\/tags?post=1296114"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}