The Glendale City Council recently considered a 160-acre land annexation for Project Eagle, located west of the northwest corner of Litchfield Road and Olive Avenue — approximately 1 mile north of Luke Air Force Base. The proposed land use for the property includes three data centers, totaling 1.1 million square feet, and a gas generation plant.

Amid the discussion, multiple speakers voiced their thoughts on the proposed annexation.

“This project has been before so many different boards and each time it has passed — it has the Luke Air Force Base approval, otherwise the board of supervisors would’ve said no,” Surprise resident Lisa Everett said. “The people who are concerned about this, I hear them and I understand their concerns — but if not this project, what would they accept?

“Change is hard and it’s different — but the reality is the sky is not falling.”

“I’m not opposed to economic development — my concern is that the proposed protections for the nearby neighborhoods are simply not adequate for a development of this size,” said Troy Mortensen, a Waddell resident who said he lives 2,000 feet from the project site. “The proposed PAD relies primarily on 75-foot setbacks, 6-foot-high walls and limited landscaping as a transition for this massive industrial campus.

“Growth and neighborhood protection are not mutually exclusive — we can have both.”

As the purpose of the public hearing was to give the public an opportunity to provide feedback, the City Council did not make any final decision with regard to the land annexation. Senior Planner Sydney Tirella explained that the adoption of the annexation application and rezoning is expected to return to the dais on Oct. 27 for further consideration.

According to Tirella, the project is organized in phases, with the data centers and turbines being constructed in phases one and two. Phase three will include an APS substation in the northeastern corner of the site.

The proposed access points for the project site include Hatcher Road to the west and Olive Avenue to the south. Tirella said that in its future phases, the site will also include access to the north via the extension of the 143rd Avenue alignment to Peoria Avenue.

As it stands, the Maricopa County jurisdiction zoning for the 160-acre land package is IND-3, for heavy industrial with an approved military compatibility permit — which would become M-2 once the annexation is complete. To accommodate the proposed data centers and gas generation plant, the city would need to rezone the property to Planned Area Development (PAD). The property sits within Luke Air Force Base’s noise contours and is designated for Luke-compatible land use under Glendale’s General Plan.

Following the staff presentation and public comment section, Councilmember Leandro Baldenegro asked whether the taller walls, berms, trees and other protections Mortenson noted in his argument could be added. Project attorney Edwin “Ed” Bull clarified that the proposal did include some of the protections, including a block wall at least 8 feet high along portions of the site, as well as “landscaping where it’s appropriate.”

“Maybe not to the degree they’re requesting them — but what was deemed appropriate setbacks, appropriate walls, appropriate landscaping, other screening mechanisms and so on is all part of what’s included in the County approval, and as part of what’s being brought forward in your design review analysis,” Bull said.

Additionally, Mayor Jerry Weiers asked Bull to clarify whether Luke Air Force Base had any issues with the project. Bull explained that the base issued a letter that lists certain conditions of approval that his client, the applicant, agreed to.

Vice Mayor Ray Malnar also asked about the distance between the project and land available for future residential development — noting that “there’s a pretty big distance between the property and the next available property that can be developed for residential.” The attorney confirmed and explained that statutory, General Plan and zoning limitations exist to regulate what development can exist around the project site.

Councilmember Lupe Conchas asked whether similar developments combining large-scale data centers and on-site power generation have been successfully developed elsewhere in the country. Bull described the configuration as an “evolving trend,” but said he could not cite a completed example during the meeting and would provide additional information when the project returns to council.